Terna Energy pumped storage station construction in October

Terna Energy has taken a final investment decision, worth 500 million euros, on the development of a pumped storage station complex in Amfilohia, northwestern Greece, whose construction is planned to begin in October and be completed within four years, the company’s hydroelectric projects director, Yioula Tsiknakou, has informed an IENE online workshop on energy storage.

The complex is planned to generate a total of 816 GWh, annually, and offer a total installed capacity of 680 MW (production) and 730 MW (pumping).

It will consist of two independent upper reservoirs, Agios Georgios and Pyrgos, with respective capacities of approximately 5 and 2 million cubic meters, and power utility PPC’s existing common lower reservoir, Kastraki Lake, developed in 1960.

Over 70 percent of the investment’s funds are planned to stem from the Greek market.

Its construction is expected to create approximately 1,200 jobs while a 100-member workforce will be employed once the unit is in operation.

Pumped storage stations are the most appropriate form of technology for mass energy storage, Tsiknakou, the Terna Energy official, told the IENE workshop.

Pumped storage stations are nowadays the most widespread mass energy storage solution, representing over 94 percent of installed energy storage capacity and offering total capacity of 161 GW around the world.