RAE starts target model delay investigation, hearing possible

RAE, the Regulatory Authority for Energy, has launched an investigation seeking to pinpoint the causes behind the delay of the target model’s first stage.

An April 10 deadline was missed for trial runs of all market systems in a procedure involving power grid operator IPTO, the energy exchange and EnexClear.

IPTO was unable to complete the development of a balancing market platform needed for the trial runs. The operator attributed its delay to a coronavirus-related inability by General Electric to deliver required software on time. This delay has now clocked up some 60 days.

The energy authority wants to determine whether any other factors, besides the coronavirus pandemic’s inevitable effect, have played a role in the delay of the trial run.

RAE also wants to examine the impact of the delays until now on the target model’s next stages. A full-scale launch scheduled for June 30, when day-ahead, intraday and balancing markets are expected to begin operating, now appears to be out of the question, while a delay beyond summer is feared.

The authority could summon all parties involved to a hearing to determine whether penalties need to be imposed.