PPC defers crucial lignite units SPA meeting for next Tuesday

A main power utility PPC board meeting scheduled today for a presentation of proposed SPA terms concerning the Meliti and Megalopoli power stations included in a bailout-required sale package of lignite units, has been postponed until next week, the session’s new date being April 23, when the utility’s financial results for 2018 will be announced, sources have informed.

SPA details, pivotal for the interest of investors, have yet to be finalized. Today’s deferral suggests last-minute efforts are being made to embellish Meliti and Megalopoli as more appealing prospects for investors. PPC was recently forced to relaunched its sale of lignite units after an initial effort failed to produce a result.

Sources with inside information on the proceedings have contended that no major changes have yet to be made to previous SPA terms.

“PPC’s disinvestment effort once again finds itself at a crucial stage, given the EU’s adverse regulatory framework concerning carbon,” one source stressed, adding that the sale’s details remain murky despite efforts by the board to clarify.

An agreement reached between PPC and the operator of the Ahlada lignite mine feeding the Meliti power station, for a lignite supply price reduction to 16.5 euros per ton from 23 euros per ton, has yet to be uploaded to the sale’s virtual data room.

Whether the units up for sale will be eligible for CAT remuneration also remains unclear. The European Commission has yet to respond to a Greek request on the matter.