Operator prioritizing grid projects for RES penetration

Distribution network operator DEDDIE/HEDNO, driven by the necessity to accommodate for increased penetration of renewable energy sources, is currently engaged in a comprehensive evaluation process to identify the segments of the network that should be prioritized for reinforcement work.

As noted by the operator in its response to a related comment submitted during consultation of its development plan for 2022 to 2026, prioritization of grid reinforcement projects aimed at increasing RES penetration has been based on the level of activity at respective substations, technical feasibility of infrastructure reinforcement, and the possibility of connecting additional RES units to the grid, in cooperation with the System Operator.

The most mature reinforcement projects are being promoted for immediate implementation and financing through the Recovery Fund, the operator added.