New Peloponnese RES project applications deferred to 2021

Distribution network operator DEDDIE/HEDNO and power grid operator IPTO have written off any possibility of accepting new RES connection applications in 2020 for new solar and wind energy projects, as well as other technologies, but application procedures could recommence in 2021, energypress has been informed.

Authorities face the challenging task of managing an enormous level of RES investment interest, especially for solar energy projects, before procedures for new-project applications can restart.

In the Peloponnese, where RES development has been held back by system saturation for seven years, a new IPTO study is still needed on the capacity to become available once two transmission networks, the west and east corridors, are completed.

Once IPTO has delivered this study, RAE, the Regulatory Authority for Energy, should lift its saturation-related ban on new RES projects in the Peloponnese and also set capacities available for each technology – wind, solar, small-scale hydropower, biomass-biogas.

However, IPTO’s delivery of the west and east corridors in the Peloponnese does not promise a complete solution as these lines, limited to 400-KV capacities, are well below capacities represented by the level of investment interest.

A fair and effective competitive procedure serving as a selection process will need to be established.