IPTO seeks Green Aegean grid link’s entry into ENTSO-E plan

Greek power grid operator IPTO intends, within the next few days, to submit a Green Aegean grid interconnection plan, envisaged to run from Greece to Germany’s south, to the ten-year development plan of ENTSO-E, promoting closer cooperation across Europe’s TSOs to support the implementation of EU energy policy and achieve Europe’s energy and climate policy objectives.

The project’s inclusion in the development plan of ENTSO-E, representing operators from all of the EU’s 27 member states, would represent a significant first step towards PCI/PMI status for the project, securing EU funding, as planned by IPTO.

The Green Aegean grid interconnection project is seen as vital for channeling, further north in Europe, huge quantities of green energy that are expected to enter Greece in the coming years from the Middle East and Asia through projects such as the Saudi Greek Interconnection. The project would also allow Greece to export some of its excess domestically-produced energy.

Greek and Saudi delegations met yesterday to establish a 50-50 joint venture for the Saudi-Greek Interconnection, with IPTO and Saudi Arabia’s National Grid as shareholders.

The Greek-German Green Aegean grid interconnection; the Saudi-Greek interconnection; along with Euroasia Interconnector, planned to connect the Greek, Cypriot and Israeli grids; as well as the Greek-Egyptian GREGY grid link, all represent parts of a green-energy intercontinental axis running several thousands of kilometers and involving many individual interconnections and special purpose companies. All these initiatives share one common goal, to transport, via Greece, renewable energy from Asia and the Middle East to green energy-hungry markets of Europe’s north.