Georgian energy market opportunities to be discussed at Tbilisi event

Georgian energy market opportunities will be discussed at the upcoming Energy Week Georgia 2020, a high-level event scheduled for January  28-30 in Tbilisi with the support of the Ministry of Economy and Sustainable Development of Georgia.

Investors, EPC and engineering companies as well as international contractors will be participating.

The energy sector of Georgia is very attractive in terms of its untapped potential, developing infrastructure and increasing local and regional demand. In particular, investors and developers are seeing increasing renewable energy opportunities in the country.

RE Market Opportunities Appealing

Domestic demand is expected to almost double by 2030 from current consumption of 13.4 TWh. Georgia’s generation capacity will not be enough to meet domestic demand in the long term without additional generation sources. The estimated deficit by 2025 is more than 3 TWh.

Starting from 2008, Georgia has liberalized and deregulated the energy market. The State Program Renewable Energy 2008 stipulates the rules and procedures regarding construction of new renewable energy projects. The electricity may be sold to any buyer in Georgia, based on freely negotiated prices, and/or to the electricity market operator (ESCO) based on the guaranteed power purchase agreement.

Georgia has well-developed transmission grid infrastructure. The whole territory of the country is covered with over 3,000 km of high, medium and low voltage lines and about 100 substations. In 2013, a new 400 KV line with HVDC back-to-back substation connecting Georgia with Turkey was commissioned, adding to already significant transmission capacity with all neighboring countries.

Major Potential for Hydropower

Georgia is one of the top countries in terms of water resources per capita and more than 80% of total electricity in the country is generated by HPPs. At the same time, only 25% of economically feasible hydro potential is exploited today.

There are 118 ongoing HPP projects, divided by the following categories:

  • 74 projects up to 13 MW – total installed capacity 363 MW and about $ 400 million investment;
  • 44 projects from 13 MW – total installed capacity 2 986 MW and about $ 5.7 billion  investment.

Wind and Solar Considerations

Georgia has significant wind potential through which average annual electricity generation is evaluated at 4 bln. KWh and installed capacity of 1,500 MW. There are 18 wind energy projects on feasibility study stage with a total installed capacity of 462 MW. Among largest projects are Imereti 1 Wind Farm (300 MW), Central Wind Farms (120 MW), Pirveli Wind Farm (110 MW) and Kartli 2 Wind Farm (100 MW).

There are 6 solar projects at feasibility and construction stages with a total installed capacity of 93 MW. Among largest projects is a 50 MW AE Power Tbilisi Solar Farm.

For further information on Energy Week Georgia 2020, visit www.geenergyweek.com