Crete link environmental terms, needed for contracts, soon

The energy ministry will publish the environmental terms for Crete’s major-scale grid interconnection with Athens, needed for project contracts, within the first ten days or March, power grid operator IPTO, the project’s promoter, anticipates.

The delivery of these terms will enable the winning bidders for the project’s cable installations, Prysmian, Nexans and Hellenic Cables – NKT, to sign project contracts with the operator, probably two to three weeks later, somewhere between late March and early April.

Meanwhile, appraisals of offers submitted by bidders for project converter stations are believed to be nearing completion. Two consortiums, Terna-Siemens and Mytilineos-General Electric-Nari have submitted offers to the tender for converter stations.

Construction of the major-scale grid interconnection, from Crete to Athens, will be able to commence once the cable and converter station contracts have been signed.

IPTO insists the project will be fully operational in 2023.

Work on Crete’s small-scale grid interconnection with the mainland, from Crete to the southern Peloponnese, is progressing as scheduled, IPTO has informed.

The installation of this segment’s submarine cables, awarded to Prysmian and Hellenic Cables, is scheduled to be completed around November, according to IPTO’s schedule.

This segment involves deep-sea cable installation work at more than 1,000 meters below sea level, an effort said to be unprecedented anywhere in the world.