Cretan grid set for revamp to enable 2 GW in RES projects

The imminent completion of an electrical grid interconnection to link Crete with Athens, a prospect now just months away, will pave the way for a full transformation of Crete’s network through upgrades of existing cables and development of new lines which, once ready, will enable the island’s grid to host just over 2 GW in renewable energy projects.

Power grid operator IPTO’s deputy chief Giannis Margaris discussed project details on Cretan TV during a visit to the island to oversee work on the grid interconnection with Athens.

The choice of the Damasta area, located in the island’s mid-north, as the finishing point of the Athens-Crete cable, is strategically positioned to facilitate power distribution to the rest of the island, the IPTO deputy noted during the interview.

IPTO’s planning takes into account Crete’s grid interconnection with the Peloponnese and – its extension to – Athens; a plan to link the Greek electrical grid, from Crete, with those of Cyprus and Israel; development of new RES units on Crete; as well as the energy security factor, or the ability to reverse energy flow should any emergency arise due to technical issues.

IPTO’s ten-year development plan covering 2024 to 2033, which has been submitted to RAAEY, the Regulatory Authority for Waste, Energy and Water, for approval, includes projects designed to reinforce the Cretan grid.

These are budgeted at 12.9 million euros, until 2024, and 12.79 million euros, until 2025, with a completion target set for 2027.