Alexandroupoli FSRU, arriving 1Q, to offer 45,000 MWh daily

The Alexandroupoli FSRU, scheduled for launch at the country’s northeastern port in the first quarter, is planned to start operating by supplying roughly 45,000 MWh of natural gas into the Greek network daily, a major sufficiency boost for the domestic system.

The facility, set for launch by March 10, will initially offer an annual capacity of 1.5 bcm, or 27 percent of its annual capacity, to the Greek system. A further 4 bcm quantity will be supplied to the Bulgarian network via the IGB grid interconnection, and, by extension, Romania, North Macedonia, Serbia, and in any markets where traders that have signed contracts with Gastrade, the project’s consortium, have customers.

An initial LNG load, to be used for testing, is scheduled to reach the Alexandroupoli LNG on January 20. It will not stem from Russia as the project is designed to contribute to ending southeast Europe’s reliance on Russian gas.

The testing stage will entail filling a 28-kilometer gas pipeline, running mostly underwater, that connects the terminal with the Greek gas system, in order to check all systems and correct any minor issues so that the FSRU can be ready to operate commercially after six to seven weeks, or early March.

The FSRU, comprised of a floating storage unit with a capacity of 153,500 m3 and three gasification units, offering daily gasification capacity of approximately 22.5 million m3, is a project of national significance that reinforces Greece’s role as an energy gateway to the markets of the wider region.