Alexandroupoli FSRU investment decision later in ’20

Investors behind the Alexandroupoli FSRU are expected to make final decisions on the project’s development in the final quarter of this year.

Two pending issues, the completion of a regulatory framework for the project, as well as approval by the European Commission’s Directorate-General for Competition of the project and funding via the National Strategic Reference Framework (2014-2020), are expected to be resolved by the final quarter.

Also, RAE, the Regulatory Authority for Energy, is soon expected to reach a preliminary decision exempting the FSRU from compulsory access to third parties as well as tariff adjustments every three to four years. This decision, needed for the project’s regulatory framework, is expected by late October or early November, when the European Commission’s approval is anticipated.

The Directorate-General for Competition will also need to give the green light for NSRF funding.

Once these pending issues are all resolved, investors will be able to decide on the project’s development, expected to require two years to construct. Investors envision a launch in 2023.

Yesterday’s anticipated entry of Bulgartransgaz, for a 20 percent stake, highlights the project’s regional prospects. This regional dimension will be highlighted even further if ongoing Romanian interest is materialized.  Talks that have been going on for some time were disrupted by the pandemic.

For the time being, Greek gas utility DEPA, Gaslog and Bulgartransgaz each have 20 percent stakes, while the Copelouzos group holds a 40 percent share. The entry into the project of Gastrade, as a fifth partner, remains pending.

Most crucial for the project’s prospects, a market test completed in March showed that the Alexandroupoli FSRU is sustainable. The test prompted a big response from Greek and international gas traders, who placed capacity reservation bids for a total of 2.6 billion cubic meters per year.

US interest for LNG supply via the Alexandroupoli FSRU is strong. Last year, Cheniere sold a big shipment to Greek gas utility DEPA, while a further ten American shipments have been made so far this year.