Turbine installed at GEK TERNA-Motor Oil gas-fueled power station

A Siemens HL-class gas turbine, the first to be used in Greece, has been installed at a prospective 877-MW state-of-the-art combined cycle, gas-fueled power station being developed by GEK-TERNA and Motor Oil Hellas in Komotini, northeastern Greece, planned to be launched in early 2024, Motor Oil Hellas has announced.

The project, Thermoilektriki Komotinis, an investment estimated to be worth 375 million euros, promises to be one of the most efficient power plants in Greece. Once operational, it will emit 75 percent less CO2 than lignite-fired power plants.

Thermoilektriki Komotinis is the second gas-fueled power station that has undergone development in Greece over recent years, following the construction, by the Mytilineos group, of an 825-MW unit in Viotia, northwest of Athens, whose commercial launch is imminent.

Construction of a third gas-fueled power station, in Alexandroupoli, northeastern Greece, as a joint venture by power utility PPC, gas utility DEPA and the Copelouzos group, is scheduled to officially commence this Saturday.

The country requires at least three additional power stations to secure energy sufficiency, according to a recent study conducted by power grid operator IPTO for 2025 to 2035.