Desfa-Gek Terna, Energean to S. Kavala UGS tender 2nd rnd

DESFA-GEK TERNA and Energean Oil & Gas have advanced to the second-round, binding-offers stage of a tender offering use, development and operation of an underground natural gas storage facility (UGS) in the almost depleted natural gas field of “South Kavala”, while China’s CMEC-MAISON GROUP failed to qualify, privatization fund TAIPED has announced in a statement.

Following the signing of confidentiality agreements, the two qualifiers will be granted access to the tender’s virtual data room, where financial and technical data will be uploaded for due diligence procedures.

However, much work lies ahead before this project matures to enable the submission of binding offers. A number of regulatory issues remain pending, officials monitoring developments have informed, describing the project as complex and highly technical.

Pending issues include determining the percentage of the UGS’s capacity to be regulated for pre-determined earnings, and the percentage of capacity whose earnings will be shaped by market forces. The regulatory period and WACC level also need to be decided and set.

Given these tasks, as well as obstacles raised by the pandemic, binding offers are not expected to be submitted any sooner than late-2021. The final stage of this tender appears most likely to take place early in 2022.

Privatization fund names 2nd round qualifiers for tenders

HRADF pre-qualifies interested parties for the next phase of the tenders of Alexandroupolis and Kavala ports, the UGS “South Kavala” and the lease of smelting plant, mines and relevant mining rights owned by the Hellenic Republic

The Board of Directors of the Hellenic Republic Asset Development Fund (HRADF) convened today and pre-qualified the interested parties that meet the eligibility criteria to participate in Phase B (Binding Offers Phase) of the following tender processes:

  • Alexandroupolis Port Authority

The HRADF’s BoD decided that four interested parties meet the criteria to participate in Phase B for the acquisition of a majority stake of at least 67% of the “Alexandroupolis Port Authority” (in alphabetical order):

  1. Consortium composed of the companies CAMERON S.A.- GOLDAIR CARGO S.A.- BOLLORE AFRICA LOGISTICS
  2. Consortium INTERNATIONAL PORT INVESTMENTS ALEXANDROUPOLIS, composed of the companies BLACK SUMMIT FINANCIAL GROUP – EUROPORTS-EFA GROUP and GEK TERNA
  3. QUINTANA INFRASTRUCTURE &DEVELOPMENT
  4. THESSALONIKI PORT AUTHORITY S.A.

 “Philippos II” port, operated by Kavala Port Authority

For the tender of the sub-concession of the right to use, maintain, operate and exploit a multi-purpose terminal within “Philippos II” port (currently operated by Kavala Port Authority S.A. – O.L.K. S.A.), the Fund’s BoD pre-qualified the following Interested Parties (in alphabetical order):

  1. Consortium composed of the companies IMERYS GREECE S.A. – GOLDAIR CARGO S.A. – I.M.G. S.A.
  2. Consortium INTERNATIONAL PORT INVESTMENTS KAVALA, composed of the companies BLACK SUMMIT FINANCIAL GROUP – EFA GROUP and GEK TERNA
  3. QUINTANA INFRASTRUCTURE & DEVELOPMENT
  4. THESSALONIKI PORT AUTHORITY S.A. 
  • UGS “South Kavala”

The Fund’s BoD pre-qualified two interested parties to participate in Phase B (Binding Offers Phase) of the tender for the concession of the use, development and operation of an underground natural gas storage facility (UGS) in the almost depleted natural gas field of “South Kavala”.

The pre-qualified interested parties are (in alphabetical order):

  1. DESFA-GEK TERNA
  2. ENERGEAN OIL & G.A.S. 
  • Smelting plant, mines and relevant mining rights owned by the Hellenic Republic

For the lease of the Larymna smelting plant, the Larymna and Loutsi mines and relevant mining rights and other assets owned by the Hellenic Republic and currently leased to “LARCO General Metallurgical & Mining Company S.A.” (LARCO), in Phase B of the tender will participate the following interested parties (in alphabetical order):

  1. COMMODITY & MINING INSIGHT IRELAND LIMITED
  2. GEK TERNA S.A. – AD HOLDINGS AG
  3. MYTILINEOS S.A.
  4. SOLWAY INVESTMENT GROUP LIMITED
  5. THARISA PLC
  6. TRAFIGURA GROUP Pte Ltd.

Following the signing of the relevant confidentiality agreement, the pre-qualified investment schemes for each tender will receive the documents of phase B’ (submission of Binding Offers) and will grant access to the virtual data room (VDR), where data and information related to the assets and the tenders will be uploaded.

Energy privatization plans delayed by negative conditions

The government has decided to slam the brakes on procedures for major energy-sector privatizations, preferring to defer bidding deadlines as a result of a series of administrative hurdles and external factors, exacerbated by challenges and uncertainties caused by the pandemic over the past year.

Binding-bid deadlines for the sales of two gas utility DEPA offshoots, DEPA Commercial and DEPA Infrastructure, initially planned for this month by privatization fund TAIPED, will now be reset for early autumn, sources have informed.

Lockdown measures have prevented possible buyers from visiting the DEPA Commercial and DEPA Infrastructure headquarters and facilities as part of their due diligence procedures.

In addition, an ongoing legal battle between DEPA Commercial and ELFE (Hellenic Fertilizers and Chemicals) has also unsettled potential buyers. According to sources, investors are demanding protection in the form of guarantees should any court verdict require DEPA Commercial to compensate ELFE over a gas-pricing dispute.

As for issues surrounding the DEPA Infrastructure sale, Italy’s Eni, currently holding a 49 percent stake in EDA THESS, a DEPA Infrastructure subsidiary distributing to the Thessaloniki and Thessaly areas, wants to sell its stake. Officials are now examining a solution that would enable the DEPA Infrastructure privatization to be completed and followed up by the sale of Eni’s 49 percent stake in EDA THESS.

TAIPED’s announcement of second-round qualifiers in a tender offering development and operation of an underground gas storage facility (UGS) in the almost depleted natural gas field of “South Kavala” in northern Greece is expected in April. But the overall procedure will not be completed until next year.

A privatization plan for ELPE (Hellenic Petroleum) has been put on hold given the unfavorable conditions surrounding the global oil industry at present.

South Kavala UGS tender qualifiers by early February

Greece’s privatization fund TAIPED will finalize its list of second-round qualifiers in a tender offering development and operation of an underground gas storage facility (UGS) in the almost depleted natural gas field of “South Kavala” in northern Greece by late January or early February, sources have informed.

Three parties submitted first-round expressions of interest: China Machinery Engineering Co. Ltd. (CMEC) – Maison Group; DESFA – GEK Terna; and Energean Oil & Gas (in alphabetical order).

Assessments of their supporting documents and other criteria are expected to be completed within the next twenty days.

RAE, the Regulatory Authority for Energy, still needs to deliver decisions concerning the operating framework of the UGS.

These pending issues include a RAE decision on the percentage of the UGS project’s capacity to be regulated, thus pre-determining this proportion’s revenue, and the earnings percentage to be determined by market forces.

The authority also needs to decide on the duration of the regulatory period and its WACC level.

New minister, just appointed, has issues to resolve in 2021

Kostas Skrekas, just appointed new energy minister as part of the government’s cabinet reshuffle, in place of Costis Hatzidakis, who has headed the ministry for a constructive year and a half, faces a series of pending energy-sector matters that remained unresolved in 2020. They need to be addressed as soon as possible. Developments and conditions this year will be pivotal for these matters.

Skrekas was previously deputy minister for agricultural development and food.

Also in 2021, a year during which takeovers and mergers are seen occurring in the retail electricity and gas markets, rivals will continue battling for market share gains. The target model’s launch two months ago has brought about new conditions, strengthening the positions of vertically integrated suppliers.

The need for a normalization of the target model’s new markets stands as the energy ministry’s most pressing task at present. A sharp rise in wholesale electricity prices as a result of soaring balancing market costs has deeply unsettled the market, impacting the standings of non-vertically integrated suppliers, as well as industrial enterprises and consumers, who face rising bills.

Market coupling with Bulgaria’s day-ahead market, scheduled to take place within the first three months of the new year, is the next step of the target model, a procedure designed to harmonize EU energy markets and promote competition.

New energy-intensive industrial tariffs also need to be set soon. Though essentially a matter concerning state-controlled power utility PPC and Greece’s industrial players, the cost of industrial energy is crucial for Greek industry, carrying particular political and economic weight.

Also, Greece has little time left in its negotiations with Brussels for a framework to offer third parties access to PPC’s lignite-based generation. This issue is no longer as crucial as it once was because the country’s lignite output has been drastically reduced. Even so, it remains important for independent suppliers.

A number of energy-sector privatizations could be completed this year. Gas utility DEPA’s two new entities, DEPA Infrastructure and DEPA Commercial, electricity distribution network operator DEDDIE/HEDNO, and a tender for a tender for the development of an underground natural gas storage facility (UGS) in the almost depleted natural gas field of “South Kavala” in northern Greece are all on this year’s privatization list.

In renewable energy, the ministry needs to take decisions within the first few months to clarify terms regulating the sector. RES investment interest is currently high. Steps still need to be taken in an ongoing effort to simplify RES licensing procedures, while a legal framework must be established for energy storage, offshore wind farms and hydrogen use.

 

South Kavala UGS bidders talk formations as deadline nears

Prospective bidders of an upcoming tender to offer an underground natural gas storage facility (UGS) license for the almost depleted South Kavala offshore natural gas field in the country’s north are deliberating over possible partnerships as the October 19 deadline for official expressions of interest approaches.

Greek gas grid operator DESFA, Energean Oil & Gas and GEK TERNA will participate in the tender, according to enegypress sources, while some market officials believe a Chinese company, not yet revealed, is also interested.

All three Greek companies have remained tight-lipped on possible partnership formations for the tender. GEK TERNA and Energean Oil & Gas are believed to be discussing the prospect of teaming up, while DESFA and the Chinese company will most likely enter the tender alone, energypress sources informed.

The tender, staged by privatization fund TAIPED, will offer rights for the use, development and exploitation of the virtually depleted offshore natural gas field south of Kavala as a UGS facility for a period of up to 50 years.

Investments needed for the project’s development are estimated between 300 and 400 million euros.

The field is located approximately 6 kilometers from the west coast of the island Thasos, in the North Aegean Sea, at a depth of 52 meters.