Siemens-Terna awarded converter stations contract for Crete-Athens link

Power grid operator IPTO’s fully-owned subsidiary Ariadne
Interconnection has successfully completed a tender process for the Converter Stations of the Crete-Athens Interconnection, awarding the contract to Siemens – Terna, a member of the GEK TERNA group, ADMIE (IPTO) Holding has announced. 

After the submission of an improved bid on March 26, the contract price was set at 370 million euros, of which 358.6 million euros concern the construction of the converter stations. The remaining 11.4 million euros concern maintenance of these stations.

The contract calls for a 36-month implementation period and will be signed after approval by the Court of Auditors.

The project will be included in the list of the Operational Program “Competitiveness, Entrepreneurship and Innovation” of the NSRF 2014 – 2020.

Τhe tendering procedure for the design, supply and installation of two Converters and a Substation for the DC Electrical Interconnection between Crete and Athens was launched on May 24, 2019.

The tender attracted the interest of world leaders in the industry and on November 1, 2019 the GE-Nari-Mytilineos and Siemens-Terna consortiums submitted binding offers.

The evaluation of the offers submitted by the consortiums, both of which possess strong technical backgrounds and specialized experience in similar projects abroad, required more than four months due to the project’s elevated technical demands. 

The technical evaluation was completed on March 13 and the Siemens-Terna consortium’s offer qualified, taking into account all relevant issues related to the interconnection.

Commenting on the tender, the IPTO group’s CEO Manos Manousakis noted: “During these challenging times, the tender process for our
flagship project, amounting to 1 billion euros, was successfully completed without problems.
IPTO will continue to focus all its efforts in order to protect the timely implementation of the project and ensure the safe and reliable power supply of Crete through the mainland system by 2023. Apart from the economic benefits of the interconnection of Crete for all Greek consumers, through the decline of Public Service Obligations (PSO), the implementation of this
project paves the way for accelerated RES integration on the island based on the principles of sustainable development.”

Crete link environmental terms, needed for contracts, soon

The energy ministry will publish the environmental terms for Crete’s major-scale grid interconnection with Athens, needed for project contracts, within the first ten days or March, power grid operator IPTO, the project’s promoter, anticipates.

The delivery of these terms will enable the winning bidders for the project’s cable installations, Prysmian, Nexans and Hellenic Cables – NKT, to sign project contracts with the operator, probably two to three weeks later, somewhere between late March and early April.

Meanwhile, appraisals of offers submitted by bidders for project converter stations are believed to be nearing completion. Two consortiums, Terna-Siemens and Mytilineos-General Electric-Nari have submitted offers to the tender for converter stations.

Construction of the major-scale grid interconnection, from Crete to Athens, will be able to commence once the cable and converter station contracts have been signed.

IPTO insists the project will be fully operational in 2023.

Work on Crete’s small-scale grid interconnection with the mainland, from Crete to the southern Peloponnese, is progressing as scheduled, IPTO has informed.

The installation of this segment’s submarine cables, awarded to Prysmian and Hellenic Cables, is scheduled to be completed around November, according to IPTO’s schedule.

This segment involves deep-sea cable installation work at more than 1,000 meters below sea level, an effort said to be unprecedented anywhere in the world.

Swift solution needed for Crete link project’s local resistance

The energy ministry is working to overcome resistance raised by regional authorities in Crete against the installation of a converter station needed for a submarine electricity grid interconnection project to link the island with Athens.

Cretan regional authorities have delivered a negative report on a plan by power grid operator IPTO, the project’s promoter, to install a converter station at Damasta in the Heraklion province.

The ministry needs to resolve the issue in order to issue an environmental permit for the interconnection project. The project’s completion target of 2023 could be threatened if this issue is not swiftly resolved.

A new round of talks involving top-ranked officials at the energy ministry and RAE, the Regulatory Authority for Energy, and Cretan regional authorities could be held during the current week. Alternative solutions and offsetting measures that would compensate locals for any negative impact caused by the project are expected to be discussed.

IPTO appears set to sign an agreement with Prysmian, Nexans and Hellenic Cables – NKT, the winning bidders in a tender for the project’s cables. However, the pending environmental permit is needed.

Technical aspects of bids submitted to another project tender concerning two other converter stations and a substation are currently being assessed. Two consortiums, Terna – Siemens and Mytilineos – General Electric – Nari submitted bids for this tender.

Its next stage, an assessment of financial offers submitted by the aforementioned participants, will be made early in the year, Ariadne, an IPTO subsidiary formed for the Cretan interconnection project, has informed.