Operator decides on 2nd round qualifiers for smart meters

Electricity distribution network operator DEDDIE/HEDNO has shortlisted the second-round qualifiers in a tender awarding a contract for the installation of approximately 7.5 million smart throughout the country, to replace the existing analog meters, energypress sources have informed.

The DEDDIE/HEDNO board yesterday approved the shortlist of second-round qualifiers, roughly one-third of the original field of seven candidates.

The companies disqualified failed to meet procedural requirements or quality standards, the sources noted.

Interested parties faced a mid-June deadline to submit applications to the tender. The operator’s appraisal of first-round applications required considerable time as participants were called upon to clarify various details.

The tender’s first-round participants were: US-based Itron; Switzerland’s Landis+Gyr; Elster, now a member of international group Honeywell; Protasis, a Greek firm operating in Greece as a representative of French company Sagemcom; Slovenia-based Iskraemeco; Gridspertise, founded in 2021 by Italian group Enel to market the group’s smart network technology; and Intrasoft International, which became a member of Danish-headquartered IT group Netcompany last year.

DEDDIE/HEDNO plans to complete the project by 2030. Its cost is budgeted at 829 million euros. The upgrade will offer immediate benefits, which have been evaluated at 223 million euros in the first year alone, in 2031.

 

Seven international players meet smart meters tender deadline

A total of seven major international players have expressed non-binding, first-round interest in a new tender staged by distribution network operator DEDDIE/HEDNO for procurement and installation of digital power meters around the country.

The operator launched this new tender after its previous procedure, launched eight years ago, ended up being brought to a standstill by legal battles fought between rival bidders.

The seven companies that met the new procedure’s first-round deadline, which expired last Friday following five extensions granted to interested parties, are: US-based Itron; Switzerland’s Landis+Gyr; Elster, now a member of international group Honeywell; Protasis, a Greek firm operating in Greece as a representative of French company Sagemcom; Slovenia-based Iskraemeco; Gridspertise, founded in 2021 by Italian group Enel to market the group’s smart network technology; and Intrasoft International, which became a member of Danish-headquartered IT group Netcompany last year.

First-round offers are planned to be opened at midday today, setting in motion their appraisal.

The project, entailing the installation of approximately 7.5 million smart meters in Greece, is expected to be completed in 2030 and its budget is estimated at 830 million euros.