GAP Interconnector promising additional Greek-Egyptian grid link

The GAP Interconnector project, planned to link Egypt with Greece, via Crete, promises to serve as a further step towards transforming Greece into an exporter of green energy to the rest of Europe, officials of the Eunice Group, heading the project, budgeted at 1.3 billion euros, have highlighted at a news conference.

It represents an additional Greek-Egyptian grid interconnection project, following the GREGY Interconnector, a 3.5 billion-euro project being promoted by Elica, a subsidiary of the Copelouzos group.

The GAP Interconnector project promises to reinforce Greece’s geostrategic role, making it a transmission hub to the rest of Europe for RES-generated electricity from Egypt, Andreas Borgeas, the project’s chief executive and a former California Senator, told journalists.

A feasibility study has already been conducted for the GAP Interconnector, as have oceanographic studies to map the areas concerning the project’s route, the Borgeas informed.

Two cables to offer a 2,000-MW capacity and run from coastal Matruh in Egypt to Crete’s Atherinolakko, a distance of approximately 450 kilometers, will serve as the project’s backbone. Converter stations will be installed at both these locations.

The project, whose subsea cable installations will reach as deep as 4,445 meters off Crete and 3,500 meters off Egypt, was described as “challenging” by Borgeas, the project chief, who added advanced deep-sea cable installation technology is now available.

The aim is to establish a multinational consortium for the GAP Interconnector project and induct, as a first step, the US company McDermott, one of the world’s biggest developers of subsea projects, Borgeas informed. French, Greek and Italian companies are also expected to soon join this consortium, the official added.

The GAP Interconnector project and the GREGY Interconnector are not rival projects but they will compete for points concerning PCI-PMI lists, Borgeas pointed out.

A direct, straight-line connection from Egypt to Crete planned for the GAP Interconnector offers it a comparative advantage as it is shorter and subsequently lower in cost, Borgeas noted, adding the project lies entirely within the boundaries of the Greek-Egyptian exclusive economic zone (EEZ).

It is planned to be complemented by the Southern Aegean Interconnector (SAI), a 1.5 billion-euro project to connect Athens, the Dodecanese islands, and Crete.

Greek-Egyptian grid link prospects gaining ground

A prospective Greek-Egyptian subsea grid interconnection, planned to exclusively transmit green energy from Egypt to Greece as a means of increasing the energy-mix share of renewables in Greece and the wider region, while also bolstering energy security in Europe, has gained further ground on a number of key fronts.

Political support has been expressed, progress is being achieved on the project’s engineering study, and the Copelouzos group, seeking to develop the project, is in talks with potential investors.

As for the technical side, agreements are being worked on for a detailed engineering study as well as a feasibility study for the project, whose cable installation will reach as deep as 2.7 kilometers at certain sections.

A Copelouzos group team headed by its president, Dimitris Copelouzos, has held talks in Cairo with Egyptian president Abdel Fattah El-Sisi and other leading Egyptian officials on regions where wind and solar farms could be developed to feed the Greek-Egyptian subsea cable.

The focus of these talks, also involving Egypt’s minister of electricity and renewable energy Dr. Mohamed Shaker El-Markabi, was on developing wind energy facilities in areas offering wind speeds of more than 10 meters per second. Such speeds are exceptional, well over those of locations hosting Greece’s best-performing wind energy facilities, where wind speeds reach 6.5 to 7 meters per second.

As for the solar energy sector, production tariffs of between 15 and 17 dollars per MWh offered at previous auctions in Egypt, a country offering flat land, are extremely competitive compared to prices in the Greek and Italian markets, even if energy transportation costs to Europe are taken into account.

Solar and wind energy investments offering a total capacity of 9.5 GW are planned to be developed in Egypt by the Copelouzos group, with partners, at a cost of approximately 8 billion euros. European, US, Middle East and Japanese companies have expressed interest to join the Copelouzos group for these projects.

Though investor interest for the Greek-Egyptian grid interconnection is strong, the European Commission’s stance will be crucial as it will be called upon to decide on the project’s inclusion in the projects of common and mutual interest (PCI/PMI) list, which would ensure EU funding support.

The Copelouzos group submitted its application last December. Brussels is expected to release PCI/PMI short lists in June, followed by finalized decisions in November.

PPC, DEPA, Copelouzos confirm Alexandroupoli power station plan

Power utility PPC, gas company DEPA Commercial and the Copelouzos group have finalized an investment decision for the development of an 840-MW natural gas-fueled power station in Alexandroupoli, northeastern Greece, a project budgeted at a total of 480 million euros, including supporting projects.

The project was officially approved yesterday at a shareholders’ meeting staged by Ilektroparagogi Alexandroupolis, the consortium formed by the three project partners for this venture.

PPC holds a 51 percent stake in Ilektroparagogi Alexandroupolis, DEPA Commercial has a 29 percent stake and the Copelouzos group is involved with a 20 percent stake.

The three partners behind the 480 million-euro project are believed to have already secured financing from the National Bank of Greece. They plan to begin construction imminently and have completed the Alexandroupoli project by 2025.

The Alexandroupoli power station is expected to feature the lowest variable cost among all natural gas-fueled power stations operating on Greece, meaning it will hold priority status for wholesale market entry.

Its location will enable the facility to be supplied gas directly via the Alexandroupoli FSRU, now being developed by Gastrade, a consortium established by the Copelouzos group for the development and operation of the floating LNG terminal.

The Alexandroupoli power plant will be equipped to also burn hydrogen in a mixture of up to 50 percent.

 

 

Copelouzos: Alexandroupoli FSRU to transport gas to Ukraine

Gastrade, the consortium established by the Copelouzos group for the development and operation of the Alexandroupoli FSRU, a floating LNG terminal now being developed in Greece’s northeast, will also install an additional FSRU unit at the location, the group’s chief, Dimitris Copelouzos has asserted in comments to media, noting the facility will be capable of transporting natural gas to Ukraine.

According to sources, the Copelouzos group has already held preliminary talks with officials of the embattled country on the prospect of natural gas supply from Greece’s northeast.

A second Alexandroupoli FSRU is expected to be completed in 2025, as an addition to the first terminal at the location, now nearing completion.

The Copelouzos group chief, asked by journalists on the route to be used for transporting natural gas to Ukraine, responded: “Via the pipeline that is now empty,” a reference to the Trans Balkan Pipeline, which transported Russian gas to Greece through the Sidirokastro entry point in the country’s northeast until early 2020.

This route was replaced by Turk Stream in early 2020 so that Ukraine could be bypassed.

The Trans Balkan Pipeline runs from Russia, crossing Ukraine, Moldova and Bulgaria, before branching out to Greece and Turkey.

Investments, including compressor stations in Bulgaria, will be needed to fully utilize the capacity offered by the Trans Balkan Pipeline, sources pointed out.

Turbine installed at GEK TERNA-Motor Oil gas-fueled power station

A Siemens HL-class gas turbine, the first to be used in Greece, has been installed at a prospective 877-MW state-of-the-art combined cycle, gas-fueled power station being developed by GEK-TERNA and Motor Oil Hellas in Komotini, northeastern Greece, planned to be launched in early 2024, Motor Oil Hellas has announced.

The project, Thermoilektriki Komotinis, an investment estimated to be worth 375 million euros, promises to be one of the most efficient power plants in Greece. Once operational, it will emit 75 percent less CO2 than lignite-fired power plants.

Thermoilektriki Komotinis is the second gas-fueled power station that has undergone development in Greece over recent years, following the construction, by the Mytilineos group, of an 825-MW unit in Viotia, northwest of Athens, whose commercial launch is imminent.

Construction of a third gas-fueled power station, in Alexandroupoli, northeastern Greece, as a joint venture by power utility PPC, gas utility DEPA and the Copelouzos group, is scheduled to officially commence this Saturday.

The country requires at least three additional power stations to secure energy sufficiency, according to a recent study conducted by power grid operator IPTO for 2025 to 2035.

Some investors behind CCGTs stalling, others forging ahead

Energy crisis uncertainty and the singling out of natural gas for its exorbitant price levels are factors troubling investors behind new combined cycle gas turbine (CCGT) plant projects.

Some investors have stalled their CCGT investment plans, waiting to see how developments unfold concerning gas prices and availability, while, on the other hand, more aggressive players are forging ahead.

Elpedison has yet to reach an investment decision on a new 860-MW CCGT at the company’s Thessaloniki refinery facilities. Despite having begun some preliminary work, Elpedison’s partners – HELLENiQ ENERGY, until recently named Hellenic Petroleum (ELPE), and Edison – have put their Thessaloniki CCGT project on hold to appraise international and European energy market developments.

If developed, Elpedison’s prospective 860-MW Thessaloniki facility would add to the joint venture’s two existing facilities. The HELLENiQ ENERGY petroleum group is also planning an FSRU at the Thermaic Gulf, which would establish a Thessaloniki hub for the company.

The Copelouzos group has also been troubled by the adverse market conditions. Group member Damco Energy had secured a license for an 840-MW CCGT in Alexandroupoli, northern Greece, but the high cost of natural gas and overall market uncertainty prompted the company to not go it alone and seek partners for the project.

According to sources, power utility PPC and gas company DEPA Commercial have joined Damco Energy for the Alexandroupoli CCGT. Official announcements on the partnership are expected soon.

Elsewhere, the GEK TERNA and Motor Oil groups have begun working on an 877-MW CCGT in Komotini, northeastern Greece. The former, in its publication of first-half results, noted work on the “Thermoilektriki Komotinis” project is continuing, its scheduled launch unchanged for 2024.

 

 

 

 

 

Copelouzos in talks with Italgas for Depa Infrastructure stake of 10-20%

Greece’s Copelouzos Group is interested in joining a new company founded by Italgas after acquisition of gas company DEPA Infrastructure was officially completed, the Italian buyer’s chief executive Paolo Gallo has informed media.

Italgas and Copelouzos Group are currently involved in talks concerning a stake of between 10 and 20 percent for the latter in the new DEPA Infrastructure company, a stake closer to the lower level being likeliest, Italgas’ CEO noted.

The negotiations between the two sides could last anywhere between weeks and months, while there is no definite outcome, Gallo informed.

Italgas intends to offer an overall stake of as much as 49 percent in the new DEPA Infrastructure company. No other potential partners or initiatives have been revealed.

Gallo, responding to journalist questions, said it is too early to tell if there will be any organizational changes at DEPA Infrastructure.

However, he did confirm that the current CEOs at DEPA Infrastructure’s distribution subsidiaries EDA Attiki and DEDA, two of three in total, would remain at their posts.

As for EDA THESS, DEPA Infrastructure’s other distribution subsidiary, Italgas is still in the process of completing its purchase of a 49 percent stake held in this company be Eni. Price and terms have been agreed.

Italgas will aim for further gas penetration in parts of Greece where natural gas networks already exist, the CEO noted.

 

Shipping sector developing offshore wind farm interest

The shipping industry, domestic and foreign, is expressing growing investment interest for offshore wind farms and is awaiting the emerging sector’s regulatory framework to develop such projects in Greek sea territory, energypress sources have informed.

Though plans are still nascent, a considerable number of shipping companies and shipowners are already in talks with consultants for related feasibility studies.

Conditions for shipping industry players are favorable. Their earnings have skyrocketed amid abnormal market conditions, worldwide, ever since the outbreak of the pandemic in early 2020. These higher earnings have generated additional capital for investment, prompting shipowners to consider the potential of offshore wind farms.

Anticipating strong growth in this emerging sector, metals production group Viohalco plans to proceed with an investment estimated to be worth 70 and 100 million euros, which, through subsidiary Cenergy Holdings, will merge the knowhow of group members Hellenic Cables and Corinth Pipeworks for the establishment of the world’s first industrialized unit for floating wind turbines.

Norway’s Equinor, the world’s biggest developer of offshore wind farms, has already expressed interest to develop projects in Greece, proposing an area between the Cyclades islands of Tinos, Syros and Mykonos.

In addition, TERNA Energy has reached an agreement with Ocean Winds, a partnership between EDP Renewables and Engie, for co-development of offshore wind farms offering a 1.5-GW capacity. Also, Mytilineos has reached an agreement with Denmark’s Copenhagen Offshore Partners. Hellenic Petroleum (ELPE) is currently engaged in talks with a major foreign company and Motor Oil has signed an agreement with Abu Dhabi Future Energy Company (Masdar).

Power utility PPC is currently involved in talks with at least five foreign companies, including Australia’s Macquarie, which recently acquired a 49 percent stake in PPC subsidiary DEDDIE/HEDNO, Greece’s distribution network operator. PPC is also believed to be in talks with American fund Quadum.

The Copelouzos group has joined forces with RF Energy to establish Aegean Offshore Wind Farms, a company planning to develop offshore parks offering an 850-MW capacity.

Greek shipowners own 5,514 ships, controlling 32 percent of the world’s tankers, 25 percent of bulk carriers and 22 percent of LNG carriers, the latter category being crucial for Europe’s effort to end its reliance on Russian natural gas.

 

Copelouzos’ Greek-Egyptian grid link backed by leaders

The Elica Interconnection, a Greek-Egyptian grid interconnection planned by the Copelouzos Group, has received the backing of Greek Prime Minister Kyriakos Mitsotakis and his Egyptian counterpart Abdel Fattah el-Sisi, entrepreneur Dimitris Copelouzos, founder of the group, has informed journalists.

A preceding teleconference between the leaders of the two countries, with participation from the president of the European Investment Bank Werner Hoyer, is expected to result in EU funding for the project.

According to Copelouzos, the project is budgeted at more than 3.5 billion euros, of which 1.5 billion euros will be provided by a group of Greek banks. The project is also a candidate for the PCI list, enabling EU funding support.

The Copelouzos group had set its sights on this project from as far back as 2008. Its double subsea cable, to stretch 954 kilometers from El Sallum to coastal Nea Makri, northeast of Athens, promises to transmit low-cost green energy with a 3-GW capacity, of which one third will be provided to local industries and the other two thirds exported to fellow EU members.

More specifically, on the exports, 1 GW will be transported through the Greek-Italian and Greek-Bulgarian networks, while the other 1 GW will be used for hydrogen production, most of which will be exported to other parts of Europe.

Licensing and financing procedures for the project are being hastened as a result of Russia’s war on Ukraine as the Elica Interconnection promises to offer Greece and the rest of the EU yet another alternative energy source as part of the continent’s effort to restrict its dependence on Russia.

The Elica Interconnection is planned to be completed by late 2025 or early 2026.

Gastrade decides on additional Alexandroupoli FSRU by 2025

Gastrade, the consortium established by the Copelouzos group for the development and operation of the Alexandroupoli FSRU, a floating LNG terminal planned for Greece’s northeast, has reached a decision to also install an additional FSRU unit at the location, expected to be completed in 2025, as a follow-up to the first terminal, set for completion in 2023.

The consortium’s decision for an additional FSRU in Alexandroupoli had been in the making from as far back as last summer, when the energy crisis was at its early stages, but was accelerated by the long-term turmoil now seen in relations between the west and Russia following the latter’s invasion of Ukraine last week.

Russia’s invasion of Ukraine has further highlighted the need for Europe to reduce its dependence on Russian gas as soon as possible. A completely new reality now appears to be in the making.

Southeastern Europe’s gas needs to result from Europe’s reduced energy dependence on Russia, through strategic diversification, has increased the prospect of Greece’s northeast becoming an energy hub that would facilitate gas exports in all directions, including to Ukraine.

The Gastrade consortium is comprised of five partners, founding member Elmina Copelouzos of the Copelouzos group, Gaslog Cyprus Investments Ltd, DEPA Commercial, Bulgartransgaz, and DESFA, Greece’s gas grid operator, each holding 20 percent stakes.

All five partners have agreed to offer 2 percent each so that North Macedonia can enter the consortium with a 10 percent stake.

Italgas’ DEPA Infrastructure deal to be finalized late March

The sale of gas company DEPA Infrastructure, acquired by Italgas, Italy’s biggest natural gas distribution company and the third largest in Europe, is expected to be completed in the first quarter of the year, energypress sources closely monitoring the procedure have informed.

Final sale procedures will have been completed towards the end of March, enabling Italgas to make its payment, an amount of 733 million euros, the sources noted.

The competition committee needs to approve the sales and purchase agreement, signed between the buyer and two sellers, privatization fund TAIPED and Hellenic Petroleum ELPE, on December 10, 2021.

RAE, Greece’s Regulatory Authority for Energy, also needs to issue necessary certification for the acquisition, but the competition committee’s approval is a prerequisite for this stage.

The acquisition will be fully completed once Italgas also purchases purchase gas distributor EDA THESS’s 49 percent stake held by Italy’s Eni gas e Luce, wanting to sell. This follow-up purchase of the EDA THESS stake has been set as a condition for Italgas, the winning bidder.

DEPA Infrastructure, EDA THESS’s parent company, holds a 51 percent stake in the gas distributor covering the Thessaloniki and Thessaly areas, while Eni gas e Luce, holds 49 percent.

The overall sum expected to be spent by Italgas for DEPA Infrastructure and EDA THESS’s 49 percent stake is expected to reach 940 million euros.

Then, Copelouzos group subsidiary Faethon is expected to enter DEPA Infrastructure with a stake seen ranging between 10 and 20 percent

Italgas and the Copelouzos group had reached a related agreement on this minority-stake arrangement prior to the DEPA Infrastructure tender.

Five hydrogen projects seeking inclusion on IPCEI list

Authorities at the energy and development ministries are working on approval procedures for five hydrogen-related projects involving as many companies – Damco (Copelouzos group), Snam, Energean, TAP and gas grid operator DESFA – all seeking their inclusion on the EU’s list of Important Projects of Common European Interest (IPCEI).

Damco is interested in developing a low-carbon blue hydrogen production facility in Greece’s north. The project is planned to use natural gas for the production of hydrogen, while also capturing carbon emissions.

A Damco partnership with Italy’s Snam, involved in a number of hydrogen projects, is looking to develop three hydrogen producing facilities, in Athens, Thessaloniki and Alexandroupoli, as well as hydrogen reloading railway stations.

Energean plans to develop a blue hydrogen plant of virtually zero emissions at Prinos, using natural gas and combining carbon capture and storage technology. Energean has already being given recovery fund approval and funding for this project.

DESFA, the gas grid operator, wants to develop hydrogen transmission projects.

TAP is interested in developing projects linked to the major White Dragon project – involving the country’s biggest energy groups with gas company DEPA Commercial as head coordinator, for a hydrogen producing facility in northern Greece’s lignite-dependent west Macedonia region – with the intention of transporting and exporting hydrogen to European markets through interconnections.

Once the five hydrogen projects are approved domestically, their investors will need to prove the maturity of the projects, technically and financially, in accordance with IPCEI criteria.

 

RAE, disgruntled, staging consultation for Kavala UGS price regulations

RAE, the Regulatory Authority for Energy, will discuss, at a board meeting on Thursday, business pricing regulations for a prospective underground natural gas storage facility (UGS) at the almost depleted natural gas field of “South Kavala” in the Aegean Sea’s north, before offering a proposal for public consultation ahead of a finalized decision, the authority’s president Athanasios Dagoumas told a press conference yesterday, confirming a previous energypress report.

Privatization fund TAIPED has pressed for this pending, and significant, step to be taken so that the prospective facility’s ongoing privatization can enter its final round of binding bids.

A gas grid operator DESFA and GEK TERNA partnership, as well as Energean Oil & Gas, have advanced to the second round of the project’s tender, staged by TAIPED, offering contracts for the development and operation of the facility.

In his comments yesterday, the RAE chief, clearly annoyed, noted that the process, until now, has had to overcome obstacles. He was particularly critical of DESFA, alleging the operator forwarded an unacceptable proposal as the authority’s role is to “protect the people, not help operators maximize their profit.”

DESFA proposed the development of a parallel double pipeline running from Thrace, in the country’s northeast, to northern city Thessaloniki, so that the Kavala UGS could function, according to Dagoumas, who added this would cost consumers in Greece nearly one billion euros, more than double the operator’s estimate of 450 million euros.

“There’s no way this proposal would cost 450 million euros…must be joking. Consumers in Greece would need to cover one billion euros so that the operator can make a profit,” Dagoumas argued. “They ought to be ashamed of themselves, having consumers pay one billion euros for pipelines we don’t need. This is not a colony.”

Senfluga, the consortium representing Italy’s Snam (54%), Spain’s Enagas (18%), Belgium’s Fluxys (18%) and Coupelouzos Group’s DAMCO ENERGY SA (10%), controls DESFA with a 66 percent stake. The Greek State holds the other 34 percent.

DESFA, responding to energypress questions, offered a completely different picture, insisting its Kavala UGS pipeline proposal would cost 420 million euros and is necessary as existing infrastructure is close to saturation point, especially in the north. Upgrades are needed to facilitate new infrastructure that would establish the country as a gas hub, DESFA officials noted, describing its proposal as a necessary network upgrade.

 

 

DESFA joining Alexandroupoli FSRU, development imminent

Gas grid operator DESFA is set to sign a contract next week for the acquisition of a 20 percent stake in Gastrade, the consortium established by the Copelouzos group for the development and operation of Alexandroupoli FSRU, a floating LNG terminal planned for Greece’s northeast, energypress sources have informed.

The European Commission offered its approval of DESFA’s entry into the Gastrade consortium approximately three weeks ago. The endorsement was needed as DESFA, operator of Greece’s gas grid, will also be entering an independent gas system by acquiring a 20 percent of Gastrade, making the operator the fifth member of the consortium.

Besides the Copelouzos group, currently holding a 40 percent stake, the Gastrade consortium is also made up of Gaslog Cyprus Investments, a fully owned subsidiary of Gaslog Ltd, owning and operating over 35 LNG tankers; Greek gas utility DEPA; and Bulgartransgaz, each holding 20 percent stakes. DESFA’s entry will give all partners equal 20 percent shares.

A finalized investment decision on the Alexandroupoli FSRU is expected within the first few days of 2022 so that the project can be developed and ready for launch within 2023.

The Alexandroupoli FSRU has, for years, been included on the EU’s projects of common interest (PCI) list, making the prospective facility eligible for favorable EU funding support, as its actualization will contribute to energy source diversification and also bolster energy security and competition in the wider region.

The Alexandroupoli FSRU will become the country’s fourth entry point for natural gas. It is planned to supply up to 944,000 cubic meters of natural gas per hour, or 8.3 billion cubic meters annually, and offer an LNG storage capacity of 170,000 cubic meters.

IPTO’s Adequacy Report for reserve mechanism, CRM near

Power grid operator IPTO is close to completing its updated grid Adequacy Report, expected to be ready within December for delivery to the European Commission. The report is needed to determine the shape of Greece’s proposals for a Strategic Reserve Mechanism and a Capacity Remuneration Mechanism (CRM).

The way towards completing the Adequacy Report was paved by the recent establishment of three required indices –  CONE (Cost of New Entry), VOLL (Value of Lost Load) and Reliability Standard – by RAE, the Regulatory Authority for Energy, and the energy ministry. These indices need to be factored into calculations before the Adequacy Report can be completed.

Plans for two new gas-fueled power stations, one by a TERNA-Motor Oil partnership, the other by the Copelouzos group, have emerged since assumptions made for IPTO’s study, which had been put to public consultation.

The launch of the two new units over the next few years is expected to greatly contribute to the grid’s reliability.

Damco Energy CCGT boost to 840 MW approved by RAE

A plan by Damco Energy, a Copelouzos group subsidiary, to increase the capacity of its prospective natural gas-fired power station in Alexandroupoli, northeastern Greece, from 662 MW to 840 MW has been approved by RAE, the Regulatory Authority for Energy.

The energy company now needs to make an investment decision, expected within the summer, before work on the project commences, sources informed. Its licensing procedure has been completed.

According to the sources, ESM, North Macedonia’s state electricity company, set to acquire a 25 percent in the Alexandroupoli natural gas-fired power station, is now at the final of its preparations and is currently performing due diligence.

Damco Energy is one of a number of companies that have not only decided to develop natural gas-fired power stations but also to boost capacities of their respective projects to over 800 MW.

Mytilineos was the first to do so with its plan for an 826-MW combined cycle gas turbine (CCGT unit) in Agios Nikolaos, Viotia, northwest of Athens, a project already being developed.

Following suit, Elpedison upgraded a licensed natural gas-fired power station plan in Thessaloniki to 826 MW, while, just weeks ago, GEK Terna and Motor Oil also announced an upgrade for their natural gas-fired power station in Komotini, northeastern Greece, a joint venture, to 877 MW.

Power utility PPC has also announced a plan to convert its new lignite-fired power station, Ptolemaida V, to a natural gas unit, planned to ultimately offer a capacity of over 1,000 MW by 2025.

The prospective natural gas-fired power stations, totaling 4.3 GW, are planned to fill the capacity gap that will be left by PPC’s withdrawal of lignite-fired power stations, exiting as part of the country’s decarbonization effort.

These new gas-fired units are also expected to export electricity to Balkan countries through grid interconnections with neighboring markets.

Energy investment activity rising, focus on RES projects, energy transition

Investment activity in the domestic energy sector is rising with major deals being negotiated, the main focus being on renewables and the energy transition, participants at yesterday’s Delphi Economic Forum made clear.

This activity promises significant growth for all RES technologies, even the more innovative, such as offshore wind farms and energy storage units.

Major energy players are moving to capitalize on opportunities that are emerging as the country pushes ahead with its decarbonization effort. Also, investor talks concerning domestic and international partnerships, the latter promising to secure expertise in sectors such as offshore wind farms, are in progress.

Power utility PPC, moving ahead with RES investments, aims to have launched projects with a total capacity of 1.5 GW by 2023. The utility’s redevelopment plan for the country’s two lignite-dependent regions, Ptolemaida, in the north, and Megalopoli, in the Peloponnese, is in progress.

PPC plans to invest 3.4 billion euros on RES project development in these regions, and an upgrade of their distribution networks, Konstantinos Mavros, chief executive of PPC Renewables, a PPC subsidiary, told the forum.

PPC is also expected to establish partnerships facilitating its entry into the offshore wind market. In addition, the company also aims to have formed a joint venture with German power company RWE by the end of summer for development of RES projects totaling 2 GW.

Elsewhere, energy company Mytilineos is also preparing a strategic alliance with a major international group for its entry into the offshore wind farm sector.

Mytilineos is also close to completing, this year, a major post-lignite investment in natural gas-fueled electricity generation. In addition, the company plans to develop 300 MW in wind farms and 1.5 GW in solar farms over the next two years.

Furthermore, Mytilineos plans to develop 20 energy storage projects, each with 50 MW capacity, by utilizing its immense knowhow gained in this field through involvement in such projects abroad.

Hellenic Petroleum (ELPE) is preparing RES and digital transition projects and will concurrently focus efforts to reduce carbon emissions and develop more eco-friendly products, including biofuels and hydrogen.

The Copelouzos group is nearing an investment decision on the development of a natural gas-fueled power station in Alexandroupoli, northeastern Greece. A decision is expected this summer. The group is currently engaged in talks with neighboring North Macedonia’s power utility for its possible entry into this project as a minority partner.

As for networks, power grid operator IPTO has planned numerous projects as part of a ten-year investment plan worth five billion euros. The operator anticipates new RES project penetration of 17 GW, a forecast exceeding the National Energy and Climate Plan’s goals.

DEDDIE/HEDNO, the distribution network operator, has put together a 3 billion-euro investment plan for the two next regulatory periods, each four years long. Projects include network undergrounding, service upgrades and improvement, new technologies, as well as grid digitalization projects.

Unlocking Greece’s offshore wind potential – Challenges, opportunities

Greece’s attempts to develop its untapped offshore wind potential have stalled in the past, but renewed investor interest and government commitment to set up a sound regulatory framework has strengthened its prospects.

By Dimitris Assimakis, Partner, and Minas Kitsilis, Senior Associate, Reed Smith.”

Introduction

Since 2006, Greece has taken several different approaches to the development of offshore wind projects. So far, these policy measures have had few concrete results. Given the present ambitious national energy and climate plan for the period up to 2030, dictating at least a twofold increase of the existing renewable energy capacity, the immediate necessity for new capacity due to the government’s decision to cease the operation of all existing lignite-fired power plants by 2023, as well as the existence of certain impediments to the further development of onshore wind farms, such as the availability of land, the pressure from other activities, such as tourism, and the necessity for the considerable expansion or reinforcement of the grid, offshore wind is expected to start playing an important role in the country’s pursuit of cost-effective and efficient renewable energy prospects.

For several years now other EU coastal countries with significant sea fronts have developed offshore wind projects and so this could certainly be a successful approach for the country with the most extensive coastline among all Mediterranean countries and one of the highest offshore wind potential in the region.

Therefore, aside from certain technical challenges (e.g. steep sea-bed drop-off around mainland Greece and around most of the Greek islands) and foreign affairs policy issues (e.g. territorial disputes in the Aegean Sea), a clear national regulatory framework, which adequately addresses spatial planning, licensing, grid interconnection and economic support issues, is also required in order for offshore wind technology to deliver its significant potentials in the country’s power generation mix.

Ongoing structured public discussions with interested investors and stakeholders as well as recent policy statements from the Greek Ministry of Environment and Energy are expected to result in an offshore wind-specific framework within this year that will enable the exploitation of this valuable renewable energy source also in Greece. Already, major international market players such as Ocean Winds (EDPR and Engie) in cooperation with Terna Energy, the largest renewable power producer in Greece, Iberdrola, Copenhagen Infrastructure Partners and Equinor are actively involved in these discussions, while reportedly other international investors such as Blue Float Energy and Innogy are closely following the developments in the sector. Moreover, local market players such as PPC Renewables, the renewables arm of Public Power Corporation (Greece’s largest power producer and supplier), Copelouzos group and RF Energy are actively engaged in this process. These deliberations are conducted within a very positive momentum for the offshore wind sector, following the recent release of the EU Strategy on Offshore Renewable Energy and the great technological developments in the sector, especially with respect to the imminent commercialisation of large-scale floating wind projects, which seem to be the most proper offshore wind technology for Greece given the depth of its territorial waters.

Past approaches stalled

Until mid-2010 the generally applicable licensing scheme at the initiative of interested investors was also applicable for offshore wind projects’ development, licensing, spatial planning and economic support against transparent and objective criteria and a regulated feed-in tariff through a standardised long term (20 years) power purchase agreement with the energy market operator as offtaker and dispatch priority for the power produced. In this context a large number of licence applications for offshore wind projects were filed with the competent Regulatory Authority for Energy in Greece (RAE).

However, only two fixed-bottom offshore projects were licensed by RAE in 2012, one of an approximately 500 MW capacity offshore the island of Lemnos in the north Aegean Sea and another one of 216 MW capacity offshore the port of  Alexandroupolis in the Thracian Sea. On the other hand, most of the licence applications filed within the period are still pending assessment from RAE with unclear further development options in anticipation of the new offshore wind-specific framework.

Subsequently, in mid-2010 Greece introduced a special centralised planning scheme for offshore wind projects to be rolled out at the initiative of the jointly competent Ministers of finance and economy, maritime affairs, foreign affairs, national defence, culture, tourism, environment and energy by virtue of a new provision introduced into the Renewables Law 3468/2006 (i.e. Article 6A), which rendered the previous open licensing scheme inapplicable for offshore wind projects.

That rather unclear approach entailed the strategic environmental assessment (SEA) of potential offshore project sites before the respective projects were licensed by the Minister of Environment and Energy, instead of RAE, and before they were auctioned off for construction through an open public tender process (public works procurement process) against economic exploitation by the successful bidder during the concession period; presumably through some long term power purchase agreement with the energy market operator as offtaker against an agreed feed-in tariff and dispatch priority. Environmental impact assessment (EIA) and further site planning, installation and construction works licensing until the operation period (inclusive) would follow the generally applicable legislation for renewables, except for some special provisions of law for the concession of sea areas in favour of renewable energy projects that would be anyways addressed as above.

This framework also entailed a number of implementing ministerial decisions and presidential decrees that were never adopted as this approach was never actually pursued in spite of a SEA study commissioned to this end by the Centre for Renewable Energy Sources in Greece (CRES) and presented in September 2015.

New approach required │ key issues

Licensing framework – recent developments & challenges ahead

The recent review of the Environmental Licensing Law 4014/2011 in May 2020 (i.e. by virtue of Law 4685/2020) raised certain hopes at it was aimed at simplifying and expediting the environmental licensing of projects of any type, including renewable energy projects, as well as at simplifying the first licensing milestone for renewable energy projects before RAE. Offshore wind projects are qualified as ‘special renewable energy projects’ and may benefit from the above simplified licensing framework as soon as an offshore wind-specific framework is adopted. In effect, this licensing framework reinstates the previous licensing scheme at the initiative of interested investors but ultimately, fails to provide any coherent legal certainty as it does not explicitly repeal the rather problematic provision of Article 6A of Renewables Law 3468/2006 mentioned above.

So although the general environmental licensing and the RES specific licensing framework were improved through the adoption of Law 4685/2020, there was not actually any real value for the offshore wind sector from this legislative process, since two parallel and apparently, inconsistent licensing regimes are currently in place although neither in full force and effect until Greece finally decides whether it will go on with a centralised or a develop-led planning system. Moreover, the licensing framework in place does not really address what will happen with the existing two electricity production licences granted as well as the various licence applications that are still pending assessment under the past licensing scheme.

Apparently, the envisaged new framework should provide for a consistent, coherent and well-structured licensing regime enabling as well the performance of any early development actions from the investors, in the sense that they should be allowed, on the basis of an exclusive right, to enter into a specific sea area in order to perform wind measurement campaigns and preliminary field surveys.

Spatial planning issues

The Special Spatial Planning Framework for Renewables of December 2008 provides for wind power in general and onshore and offshore wind power in particular. Such provisions include generally applicable criteria, limitations and exclusion zones for wind energy and special ones for onshore and offshore wind projects. However, it is commonly admitted that the said framework needs to be reviewed to account for technological developments and acquired experience in spatial planning and deployment of renewables not only in Greece but also in the EU, including current best practices.

The Ministry of Environment and Energy is already working on updating the framework but it will take some time to achieve concrete results due to the technical and SEA studies involved. In addition, it must also be compatible with the regional and other special frameworks for spatial planning that are also under review pursuant to Part A of Law 4417/2016 and most importantly, with the still pending maritime spatial planning for marine areas in Greece according to Part A of Law 4546/2018 (as per the relevant EU Directive 2014/89) for the avoidance of conflicts. An interim solution may have to be sought in this connection as otherwise neither central nor individual planning will be feasible and legally sound against a reasonable time schedule and certain target capacity for offshore wind development by 2030 and beyond.

Sovereign rights and public international law

Greece has reserved the right to exercise all its sovereign rights under Article 3 of the 1982 United Nations Convention on the Law of the Sea (UNCLOS) to expand its territorial sea beyond six (6) nautical miles, which is the current breadth thereof, up to twelve (12) nautical miles measured from baselines determined in accordance with the UNCLOS. Greece has signed and ratified the UNCLOS by virtue of Law 2321/1995. Recently, by virtue of Law 4767/2021, Greece has expanded its territorial sea to twelve (12) nautical miles in the whole of the Ionian Sea area up to the Cape Tainaron in south Peloponnese, while it is reiterated therein Greece’s sovereign rights to do the same with all other sea areas, including the Aegean Sea, being the area with the highest offshore wind potential.

However, given the historical tension between Greece and Turkey concerning the Aegean Sea, it is rather questionable whether Greece will finally decide to exercise such sovereign rights and expand its territorial sea to twelve (12) nautical miles also in the Aegean Sea, according to the UNCLOS, in the years to come. In this respect, it is reasonably expected that any development of offshore wind projects in the Aegean Sea will need to be limited within the six (6) nautical miles zone. Further, the establishment and delimitation of the Greek exclusive economic zone by means of valid and legally binding agreements with neighbouring states pursuant to the UNCLOS is still pending too, save for the recent agreements with Italy in the Ionian Sea and Egypt in part of the Mediterranean Sea south-east of the island of Crete.

Proper support scheme for offshore wind

The new support scheme for renewables in Greece introduced by virtue of Law 4414/2016 in line with the European Commission’s Guidelines on State aid for environmental protection and energy for the period 2014 – 2020 provides for operating aid to renewables through a technology-specific sliding feed-in premium (FiP) scheme for the vast majority of new projects which is added as a premium to wholesale market revenues and thus tops up their market revenues in order for the operating aid to reach an acceptable level of support measured against a technology-specific reference tariff (RT).

Aside from small scale and experimental projects, since 2017 the RTs are set through competitive bidding processes (auctions) on project basis for the two mature technologies (i.e. onshore wind and solar photovoltaic) in technology-specific and technology-neutral auctions run by RAE. In the event that the wholesale market price of a renewable technology exceeds the applicable RT, the excess is rebated to a special account for renewables kept by the RES operator and aggregator of last resort (DAPEEP) and hence the operating aid contract is a standardised two-way contract for differences (CfD) between the applicable RT (as strike price) and the producer’s revenues from the wholesale electricity market.

The auctions scheme is expected to extend beyond 2020, likely up to 2024 and for a certain overall capacity threshold not in excess of 2.1 GW, in accordance with the relevant statements made by the Minister of Environment and Energy in mid-November 2020.  However, technology-specific auctions for offshore wind or technology-neutral auctions including offshore wind are not likely to be feasible for Greece in this time schedule. In the meantime, previous auctions for renewable electricity have resulted in applicable RTs for onshore wind and solar photovoltaic projects below wholesale market prices for certain time periods. Therefore, alternative revenue structures involving corporate renewable power purchase agreements (PPA) cannot be excluded for onshore wind and solar photovoltaic or offshore wind projects in Greece in common with other countries where such alternatives are already pursued for some years now in the onshore wind and solar photovoltaic sectors, and recently also in the offshore wind sector. However, such structures are hardly suitable or bankable during the early days of a new sector development like offshore wind.

Optionally, individual aid without an auction process is also possible for renewable energy projects (including offshore wind) exceeding 250 MW or clusters of projects exceeding 250 MW and sharing common interconnection with the transmission system according to the said guidelines on State aid and Article 4 para 12 of Law 4414/2016. Individual aid requires prior notification to and approval from the European Commission. An implementing ministerial decision is still pending (para 12 was added to Article 4 of Law 4414/2016 in end-2019) for all renewable energy projects or clusters of such scale and importance for national and EU renewable energy targets, but it is reasonably expected soon. This option is reasonably considered more suitable, especially for floating offshore wind projects, and certainly more bankable at the early stages of any new renewable technology.

Moreover, Greece could consider when developing its national recovery and resilience plan in the context of the EU Recovery and Resilience Facility possible priority actions in order to facilitate the development of offshore wind projects in the country.

Grid connection

However, unlocking the great wind potential of the Greek seas and islands depends on the development of some critical interconnections, some of which are expected in the short to medium term. The anticipated completion of the interconnection of the island of Crete with the high-voltage system in the Athens metropolitan area by 2023 and of all Cycladic islands by 2024 will enable the significant development of new wind power capacity on these islands but also in the sea areas around them covering a significant part of the south Aegean Sea.

Moreover, ADMIE, the Greek TSO, has included in its current ten-year development plan the progressive interconnection of all other major islands in the south-eastern and north Aegean Sea, such as the islands of Rhodes, Kos, Karpathos Lemnos, Lesvos, Samos and Chios by 2029,  covering therefore though such plan the remaining of the Aegean Sea.

ADMIE is actively participating in the discussions held for the formulation of the offshore-wind specific framework and clearly, one of the key issues which need to be addressed therein is the interlink of any offshore wind investment projects with ADMIE’s development plan and its role in the design, construction and financing of the necessary grid expansion and reinforcement works.

Strategic investments programme and offshore wind

Since 2011, Greece has had in place an investments facilitation programme whereby productive investments (private or public ones, foreign or domestic) which generate quantitative and qualitative results of major significance for the national economy (including other criteria on investment budget, employment creation, innovation and sustainability) are qualified by an inter-ministerial committee as ‘strategic investments’ and are entitled to one-stop-shop and fast-track licensing and development procedures, including environmental and spatial planning ones as well as land expropriation related ones and dispute resolution provisions.

Part B of Law 4608/2019 on attracting strategic investments aims at modernising, improving and enhancing the scope of application and the fast-track licensing and development procedures in favour of strategic investments. These new provisions include: special spatial plans on project basis; tax benefits (as individual State aid subject to applicable EU regulations); one-stop-shop and fast-track licensing within 45 calendar days per licence, permit, opinion or approval (subject to special EU law provisions and procedures, e.g. public awareness on environmental matters), and overall within three (3) years from the MoU between the strategic investor and the Minister of Finance and Development on the time schedules and mutual obligations; cash grants for research and development (R&D) projects, and a UNCITRAL arbitration clause for disputes relating to the said MoU. On the other hand, applications for qualification under the new programme can be filed until the end of 2023.

Greece’s strategic investments programme has facilitated to some extent the spatial planning and licensing of a number of investments, mainly in tourism and other commercial sectors including some solar photovoltaic and solar thermal projects of scale and clusters of onshore wind projects. However, it has been limited to licensing aspects thereof and it does not address operating aid or other economic support aspects. Furthermore, it captures urban or onshore (including seashore) spatial planning, but it does not capture offshore aspects and maritime spatial planning that is still pending as described above. Therefore, account taken of the end-2023 current deadline for applications under the new programme, it is yet to be considered in more detail how the new programme for strategic investments in Greece could facilitate offshore wind. A recent positive development though is the special benefit conferred now under the programme to innovative renewable projects, amongst which offshore wind projects, in relation to their priority for grid connection over other projects using more typical renewable energy technologies, such as onshore wind and solar photovoltaic projects.

The way forward    

Experience from other jurisdictions has shown that formulating a comprehensive and appropriate legal framework for offshore wind in any given country is a challenging multi-disciplinary exercise. Structured public discussions with interested investors and stakeholders are ongoing in Greece during and have been for the last couple of years. Specific proposals are also being put forward for public consultation by stakeholders like the Hellenic Wind Energy Association but also from major global offshore wind developers. The Ministry of Environment and Energy has also announced that it will present a legislative proposal for offshore wind by mid-2021 taking into account the particularities of the Aegean Sea and international experience in offshore wind industry and technologies. We are confident that the ongoing process will result in a comprehensive legislative proposal for an offshore wind-specific framework. However, time and planning are of the essence for long lead capital intensive infrastructure investments like offshore wind to materialise within a certain time schedule, e.g. by 2030, on legally sound and commercially sensible and therefore bankable conditions in order to pursue successfully the national and EU energy, climate and environmental policies.

 

DEPA Commercial pushing to mature RES licenses in time for auction

Gas company DEPA Commercial, currently placing emphasis on its alternative business interests, is making efforts to bring to maturity solar energy licenses in time for an upcoming RES auction. These PV licenses concern solar farm projects representing a total capacity of 499.61 MW.

Late in January, DEPA Commercial announced it had acquired a 49 percent stake in North Polar, a special purpose vehicle (SPV) established on the basis of a portfolio carrying solar energy project certificates and production permits. These licenses concern projects in northern Greece’s west Macedonia region.

DEPA Commercial and its SPV partner have submitted environmental terms for these projects and are now expecting their connection terms.

The partners are striving to participate in the next RES auction to be staged by RAE, the Regulatory Authority for Energy, the first to be held under new terms expected to soon be approved by the European Commission.

On another front, DEPA Commercial is closely monitoring developments regarding the Alexandroupoli FSRU in northeastern Greece, another of its project interests.

DEPA Commercial holds a 20 percent stake in Gastrade, a company established by the Copelouzos group for the development and operation of the Alexandroupoli FSRU.

The European Commission’s Directorate-General for Competition still needs to approve Greek gas grid operator DESFA’s entry into the consortium, also with a 20 percent stake, to be taken from the Copelouzos group’s current 40 percent share in the Alexandroupoli FSRU venture.

The Brussels authority’s endorsement of DESFA’s entry is seen as a formality following its recent approval of the entry of Bulgaria’s Bulgartransgaz as a fourth member of the consortium, also with a 20 percent stake. Gaslog is the other consortium member, also holding 20 percent.

The DESFA entry approval is anticipated within the second quarter. Gastrade’s partners are then expected to swiftly follow with an investment decision on the Alexandroupoli FSRU’s construction.

Elpedison launches tender for Thessaloniki power station

Energy company Elpedison has launched an international tender for procurement of mechanical equipment concerning its 826-MW gas-fueled power station project in northern city Thessaloniki’s Diavata area, sources have informed.

The company, also moving ahead with the project’s environmental permit procedure, is expected to soon finalize its investment decision.

Besides Elpedison, a number of other energy firms are also moving ahead with gas-fueled power station plans.

GEK-TERNA is planning a 665-MW facility in Komotini, northeastern Greece; power utility PPC recently secured a license for a 665-MW unit, also in Komotini; Elvalhalkor is pursuing plans for a 566-MW unit in Thisvi; the Copelouzos group is moving ahead with a 662-MW project in the industrial area of Alexandroupoli, in the northeast; and the Karatzis group is planning a 660-MW power station in Larissa, in the mid-north.

The Mytilineos group has already begun constructing an 826-MW gas-fueled power station in Viotia’s Agios Nikolaos area, northwest of Athens, a project expected to be launched late this year or early next year.

The establishment of a permanent CAT mechanism, anticipated by the investors behind these projects, promising grid flexibility, is crucial for the investment plans.

Electricity demand levels in the Greek market as well as the course of Greece’s decarbonization effort, expected to create openings for new power stations, are also vital factors.

 

PPC granted license for 665 MW gas-fueled power station

A power utility PPC investment plan entailing the development of a 665-MW gas-fueled power station in the industrial zone of Komotini, northeastern Greece has been granted a license by RAE, the Regulatory Authority for Energy, adding to the list of licensed projects to serve as a bridge in the country’s energy transition until the renewable energy sector fully prevails.

The project linked to this latest license, given a 35-year duration, is scheduled to be launched in December, 2024.

RAE has now granted five licenses to an assortment of companies for such investment plans, though not all will necessarily be developed.

An 826-MW gas-fueled power station being developed by Mytilineos in Viotia, slightly northwest of Athens, set to be launched at the end of this year, is the most advanced of these investment plans.

The maturity levels vary for other projects in terms of environmental licensing and other procedural matters. These include a 665-MW unit planned by Terna, also in Komotini; an 826-MW project planned by Elpedison in Thessaloniki; and an 830-MW facility planned by the Copelouzos Group’s Damco in Alexandroupoli, northeastern Greece.

Also, the power utility is expected to reach a decision on converting its prospective Ptolemaida V lignite-fired power station into a gas-fueled facility.

DESFA’s Alexandroupoli FSRU entry awaiting DG Comp OK

Gas grid operator DESFA’s agreement, last November, for the acquisition of a 20 percent stake in Gastrade, the company established by the Copelouzos group for the development and operation of the Alexandroupoli FSRU, a floating LNG terminal planned for Greece’s northeast, requires, as its final step, approval from the European Commission’s Directorate-General for Competition, to officially make the operator the consortium’s fifth member.

DG Comp approval of DESFA’s agreement is needed as the operator, managing Greece’s gas transmission system, is entering an independent gas system through its agreement to buy a Gastrade stake.

The DG Comp’s endorsement of the anticipated DESFA entry is seen as a formality following its recent approval of the entry of Bulgaria’s Bulgartransgaz as a fourth member of the consortium, also with a 20 percent stake.

A finalized investment decision by Gastrade for the development of the Alexandroupoli FSRU is expected this spring. The unit’s launch is scheduled for the first half of 2023.

The FID will enable the procurement procedure for the project’s equipment to go ahead, beginning with the floating unit, for which a Gastrade tender has already been completed.

A preferred bidder has also been declared for the FSRU’s subsea-and-overland pipeline, to link the floating unit with the country’s gas grid.

Bids for a tender offering a contract for the design, procurement and construction of the project’s fixed mooring system were submitted in late-February.

Talks are still in progress, at a diplomatic level, for the possible entry into the Alexandroupoli FSRU by North Macedonia’s state gas company, through the acquisition of a 10 percent stake from Gastrade. The outcome of these talks will not affect the project’s development.

Offshore wind farm framework within first half, auction in ‘22

A legal framework for offshore wind farms will be ready within the next few months, no later than the end of the year’s first half, enabling investments in this sector to begin in Greece, the energy ministry has assured.

The energy ministry’s leadership is expected to reiterate this stance, without offering further scheduling details, at an event to be staged today by ELETAEN, the Greek Wind Energy Association. Energy minister Kostas Skrekas and the ministry’s secretary-general Alexandra Sdoukou will be participating.

Norway, a country with extensive offshore wind farm knowhow, will be strongly represented at the ELETAEN event. The Norwegian Ambassador to Greece, Frode Overland Andersen, and Daniel Willoch, a representative of NORWEA, the Norwegian Wind Energy Association, will take part.

So, too, will Giles Dickson, CEO at Brussels-based WindEurope, promoting the use of wind power in Europe.

If all goes as planned with efforts being made by the energy ministry, as well as ELETAEN, a first auction for offshore wind farms in Greece could be staged within the first half of 2022.

Considerable progress has been made in recent months, but pending issues on important details concerning spatial and licensing matters, connectivity with power grid operator IPTO’s network, as well as a remuneration formula for investors, all still need to be settled. The overall effort is complex and involves a number of ministries.

Investor interest in offshore wind farms is high as studies project electricity costs concerning floating units in Greece will experience a 40 percent decline by 2050. This cost, according to an older European Commission study, was estimated to drop from 76 euros per MWh in 2030 to 46 euros per MWh in 2050.

The same study estimated Greece’s offshore wind farm capacity would reach 263 GW, a prospect promising investors sustainability for the development of such projects.

Norway’s Equinor has already expressed the strongest interest for offshore wind energy development in Greece. Denmark’s Copenhagen Offshore Partners, also a major global player, has also shown some signs of interest.

As for Greek companies, TERNA Energy, the Copelouzos Group, and RF Energy have, in the past, submitted applications for offshore wind energy parks to RAE, the Regulatory Authority for Energy.

 

Alexandroupoli FSRU 2Q investment decision, work to start in ’21

The shareholders of Gastrade, a company founded by the Copelouzos Group for the development and operation of the Alexandroupoli FSRU planned for Greece’s northeast, are gearing up for an investment decision, expected in the second quarter, ahead of the beginning of the project’s development, anticipated within the current year.

Gastrade’s shareholders will most likely make an investment decision in May, sources informed.

The consortium’s shareholders are currently awaiting final administrative details that will formalize the entry into Gastrade of Bulgaria’s Bulgartransgaz and DESFA, the Greek gas grid operator.

Last week, Thanassis Dagoumas, the head official at RAE, the Regulatory Authority for Energy, approved the transfer of a 20 percent Gastrade stake from the Copelouzos Group’s Asimina Eleni Copelouzou to the Bulgarian gas company.

Copelouzou now controls 40 percent of Gastrade, with three stakeholders, Gaslog, DEPA Commercial and Bulgartransgaz each holding 20 percent.

Within the next few weeks, the RAE chief is also expected to endorse a further 20 percent transfer from Copelouzou to DESFA, giving the consortium’s five partners equal shares of 20 percent each.

Gastrade has already announced a tender offering an EPC contract for the floating LNG terminal in Alexandroupoli. Participants face a February 18 deadline.

An investment decision promises to push forth engineering studies, including geotechnical, as well as the order of a floating vessel for the project during the year. The FSRU will be completed in 2023, Gastrade shareholders have announced.

The shareholders appear receptive to the idea of North Macedonian involvement in the Gastrade consortium. They are awaiting bilateral developments at a diplomatic level, sources informed.

North Macedonia involvement in key Alexandroupoli projects

North Macedonia plans to help cover its energy needs through an involvement in two Greek-based projects, the prospective FSRU in Alexandroupoli, northeastern Greece, and, in the same region, a gas-fueled power station to run on LNG stemming from the floating LNG terminal.

Much progress has been made on the neighboring country’s interest in these two projects since a meeting in Athens last September between Greek Prime Minister Kyriakos Mitsotakis and his North Macedonian counterpart Zoran Zaev. The partnership also represents a strategic decision for the Greek government.

It is considered certain that a state-owned North Macedonian company will soon enter the Alexandroupoli FSRU project’s equity pool with a 10 percent stake, energypress sources have informed.

This project’s five current partners – Copelouzos group, Gaslog, Greek gas utility DEPA, Greek gas grid operator DESFA and Bulgartransgaz – are expected to each offer small portions of their respective 20 percent stakes to make available a 10 percent stake for the state-owned North Macedonian company in the Alexandroupoli FSRU.

The project’s development is not expected to be impacted by any equity reshuffles.

Two international tenders staged by Gastrade, a company established by the Copelouzos group for the development and operation of the Alexandroupoli FSRU, have been successfully completed. One of the two tender concerns the FSRU’s construction. The other concerns the installation of pipelines linking this facility to the national gas grid.

The Alexandroupoli FSRU consortium is expected to make a final investment decision in late February, sources informed.

On the other front, ESM, North Macedonia’s state electricity company, is expected to acquire a 25 percent stake in a gas-fueled power station to be developed by Damco Energy, a Copelouzos group subsidiary, in Alexandroupoli’s industrial zone.

The initiative will secure 200 MW of the facility’s 800-MW capacity for North Macedonia. The country currently has an electricity deficit of approximately 2 GWh.

Bulgarian state-owned electricity company NEK EAD also appears interested in acquiring a stake in the Alexandroupoli power station. Bulgaria has projected an electricity deficit a few years from now as the country must phase out major lignite-fired power stations. European Commission exemptions extending the lifespans of these units are expiring.

Gas market competition intensifies, TAP lowering prices

Competition has intensified in the country’s wholesale gas market at a time of changing conditions and negotiations for 2021 deals between importers and major-scale consumers, namely electricity producers and industrial enterprises.

Many gas supply contracts expired at the end of 2020, requiring a large number of players to renegotiate deals. Some of these big consumers have already reached new agreements with gas wholesalers.

Market conditions have changed considerably compared to a year earlier. Supply of Azeri gas through the new TAP route has already begun to Greece as well as Bulgaria, increasing overall supply, which has obliged, and permitted, gas utility DEPA to pursue a more aggressive pricing policy as the company pushes to absorb quantities it has committed to through clauses in existing contracts.

Also, the TAP-related increase of gas supply to Bulgaria, combined with this country’s inflow of Russian gas through oil-indexed price agreements, currently relatively cheaper, is now depriving Greek wholesale gas companies of entry into a neighboring market that was available for trading activity last year.

Furthermore, conditions have also been impacted by a competition committee decision no longer requiring DEPA to stage gas auctions to make available a share of its gas orders to rival traders. This measure was introduced and maintained to help liberalize Greece’s gas market.

The new conditions are pushing Greek traders towards more competitive pricing policies. They appear to have acknowledged that their profit margins will be narrower in 2021.

DEPA, helped by the fact that a sizeable proportion of its gas purchases is oil-indexed, is said to be playing a dominant role in the ongoing negotiations for new contracts with customers.

It should be pointed out that, unlike rival gas importers such as Mytilineos, Elpedison and Heron, all benefitting through self-consumption of a large part of their gas orders for gas-fired power stations they operate, DEPA does not self-consume.

Prometheus Gas, a member of the Copelouzos group, remains a formidable player, while the power utility PPC and petroleum company Motor Oil are less influential in the wholesale gas market.

Higher LNG prices, compared to pipeline gas, will decrease demand for LNG this year and weaken the interest of traders for LNG supply through gas grid operator DESFA’s Revythoussa terminal on the islet just off Athens. Last year, this facility was a hot spot of trading activity as a result of lower-priced LNG.

DEPA Comm VDR open; 5-year stay for Infrastructure buyer

The video data room for the privatization procedure of DEPA Commercial, one of two new gas utility DEPA entities placed for sale, is now open to prospective bidders, but initial information made available is limited to non-financial details.

Financial details on DEPA Commercial will be made available as a second step to all consultants representing the potential buyers, while a third and final stage will follow to conditionally offer bidders confidential information in person at the DEPA headquarters.

As previously reported, the second-round, binding-bids deadline for the DEPA Commercial sale, offering investors a 65 percent stake, has been extended to March, 2021.

The field of second-round qualifiers is comprised of two partnerships, Hellenic Petroleum (ELPE) with Edison and power utility PPC with Motor Oil Hellas, plus Mytilineos, TERNA, the Copelouzos group, Shell, and the Swiss-based MET Group.

As for DEPA Infrastructure, the other new DEPA entity up for sale, energy minister Costis Hatzidakis is preparing a legislative revision that will require the winning bidder to retain its company shares for a period of at least five years.

This condition will also apply for the DEPA Infrastructure subsidiaries EDA Attiki, EDA Thess and DEDA, the gas distributors covering the wider Athens area, Thessaloniki-Thessaly and rest of Greece, respectively. DEPA fully owns DEDA and EDA Attiki and holds a 51 percent stake in EDA Thess.

The DEPA Infrastructure binding-bids deadline has also been extended to the end of February, 2021. Italgas, EPH, First State Investments, KKR, Macquarie and Sino-CEEF have qualified for the final round.

 

Business plan, better results, new activities in DEPA Commercial VDR

The virtual data room for a forthcoming privatization to offer a 65 percent stake in DEPA Commercial, an offshoot of gas utility DEPA, expected to be opened for potential buyers to assess by the end of this week, will present a business plan, improved financial figures at DEPA, new company activities envisaged, as well as DEPA’s outlook on the course of the country’s natural gas market and the company’s position within it.

According to privatization fund TAIPED’s revised Asset Development Plan, participants will submit binding bids in December.

The field of first-round entries, comprising two consortiums and five companies, will have roughly three months to prepare binding bids, according to the schedule.

Hellenic Petroleum ELPE and Italy’s Edison are one of the privatization’s two participating consortiums, the other formed by power utility PPC and Motor Oil Hellas. The five individual participants are: Mytilineos, TERNA, Copelouzos group, Shell and the Swiss-based MET group.

New partnerships could be established by the field of participants as long as they do not affect the sale’s competition standards and have been approved by TAIPED.

The sale of DEPA Commercial is a major attraction for potential buyers as it offers a big slice of the wholesale and retail markets, including gas supplier Fysiko Aerio Attikis, a subsidiary covering the wider Athens area. Fysiko Aerio Attikis already serves close to 400,000 households and 10,000 businesses.

DESFA one step away from Alexandroupoli FSRU entry

Just days after the entry of Bulgaria’s Bulgartransgaz, Greek gas grid operator DESFA appears set to become the fifth member of Gastrade, the company established by the Copelouzos group for the development and operation of the Alexandroupoli FSRU, a floating LNG terminal envisioned for Greece’s northeast.

Talks concerning a DESFA entry, ongoing since the beginning of this year, have essentially concluded, while an announcement of the operator’s entry into Gastrade’s line-up is expected soon, no later than the end of September, energypress sources informed.

DESFA’s interest to join the consortium for the Alexandroupoli FSRU project, the first ever private-sector plan for such infrastructure in Greece, reflects the intention of the company’s new ownership and administration to broaden DESFA’s role from gas grid operator to a major player in Greece’s natural gas market.

As for Gastrade, keen to establish partnerships that support its strategic objectives, DESFA’s expected entry into the Alexandroupoli FSRU consortium appears to have been encouraged as a result of the operator’s knowhow, as a TSO, in LNG and the Greek gas market, its players, as well as the legal framework.

DESFA’s entry would also give the Greek State a stake in the Alexandroupoli project, supported for years by the previous and current Greek governments.

Besides the Copelouzos group, holding a 40 percent stake, the Gastrade consortium is currently also made up of Gaslog, Greek gas utility DEPA, and Bulgartransgaz, each holding 20 percent stakes. The entry of a fifth member will give all partners equal 20 percent shares.

The project, budgeted at 380 million euros, is expected to be launched no later than early 2023.

The Alexandroupoli FSRU, along with the existing Revythoussa islet LNG terminal just off Athens, are crucial given the current strains in Greek-Turkish relations as the two units represent the country’s only gas infrastructure not relying on Turkish territory.

The LNG terminals also promise to increase competition in the regional market and reduce natural gas supply costs to neighboring countries.

A market test was successfully completed for the Alexandroupoli FSRU in March.

DEPA Infrastructure VDR open, DEPA Commercial data soon

A virtual data room has just been opened for the six bidding teams preparing to make second-round offers in the privatization of gas company DEPA Infrastracture, an offshoot of gas utility DEPA.

Czech company EPH, Italy’s Italgas, the Australian investment funds First State Investments and Macquarie, US firm KKR and China’s Sino-CEEF & Shanghai Dazhong Public Utilities now have access to all relevant data concerning the DEPA Infrastructure sale.

Another VDR is expected to be opened within the next few days for bidders participating in the privatization of DEPA Commercial, DEPA’s other entity up for sale.

The participants in this sale, seven entries in total, are: Motor Oil Hellas-PPC, ELPE-Edison, Mytilineos, GEK-TERNA, the Copelouzos group, Dutch company Shell and the Swiss-based MET Group.

VDR information for the DEPA Commercial sale will be made available over three phases as a protective measure intended to ensure competition. The first phase, offering non-sensitive data, will be open for all. Access to VDR information during the second stage, offering sensitive data, will be restricted to consultants. Bidders will be offered conditional access to confidential information in the third phase.

Greece’s privatization fund TAIPED is aiming to declare preferred bidders for both sales in the final quarter of this year. Market officials, however, believe this is more likely to occur in the first quarter of 2021.

DEPA Commercial bidders are allowed to team up and establish consortiums but partnerships for the DEPA Infrastructure sale are not permitted.

Bidders participating in the DEPA Commercial sale are mainly eyeing the company’s prized asset, retail gas supplier and subsidiary Fysiko Aerio Attikis, covering the wider Athens area. This company already serves close to 400,000 households and 10,000 businesses.