Swift solution needed for Crete link project’s local resistance

The energy ministry is working to overcome resistance raised by regional authorities in Crete against the installation of a converter station needed for a submarine electricity grid interconnection project to link the island with Athens.

Cretan regional authorities have delivered a negative report on a plan by power grid operator IPTO, the project’s promoter, to install a converter station at Damasta in the Heraklion province.

The ministry needs to resolve the issue in order to issue an environmental permit for the interconnection project. The project’s completion target of 2023 could be threatened if this issue is not swiftly resolved.

A new round of talks involving top-ranked officials at the energy ministry and RAE, the Regulatory Authority for Energy, and Cretan regional authorities could be held during the current week. Alternative solutions and offsetting measures that would compensate locals for any negative impact caused by the project are expected to be discussed.

IPTO appears set to sign an agreement with Prysmian, Nexans and Hellenic Cables – NKT, the winning bidders in a tender for the project’s cables. However, the pending environmental permit is needed.

Technical aspects of bids submitted to another project tender concerning two other converter stations and a substation are currently being assessed. Two consortiums, Terna – Siemens and Mytilineos – General Electric – Nari submitted bids for this tender.

Its next stage, an assessment of financial offers submitted by the aforementioned participants, will be made early in the year, Ariadne, an IPTO subsidiary formed for the Cretan interconnection project, has informed.