Revythoussa truck loading station soon, LNG jetty in 2022

The development of a truck loading station at the Revythoussa islet LNG terminal just off Athens will be completed and launched by the end of the year, energypress sources have informed.

Also, a new small-scale LNG jetty to serve the truck loading station, and, amongst other things, contribute to LNG bunkering at the nearby Piraeus port, will be ready in autumn next year, the sources added.

The truck loading station is part of gas grid operator DESFA’s ten-year development plan that includes a category for small-scale LNG project installations, worth 40.5 million euros.

According to the ten-year development plan, the new small-scale LNG jetty, budgeted at 20.4 million euros, will be installed at the northeastern section of Revythoussa.

DESFA has already applied for funding support through the National Strategic Reference Framework (2014-2020) that would cover 50.42 percent of the small-scale LNG jetty’s cost.