Production license applications concerning new RES projects have continued at a steady rate, while the balance between various technologies has remained unchanged, industry figures for June have shown.

Solar energy production license applications, numbering 126 of the overall 215 submitted in June, continued to hold the lion’s share and represented 2.1 GW of the 2.5 GW total.

As for wind energy, license applications for 76 projects with a total capacity of 384.71 MW were submitted in June. A total of 12 small-scale hydropower applications were made for a capacity of 10.03 MW. One cogeneration, or combined heat and power (CHP), application representing a capacity of 2 MW was made.

A total of 14 companies submitted multiple applications representing 119 projects with a capacity of 1,757.5 MW, of which 196.9 concern wind energy stations.

The 14 multiple applicants were: Juwi Hellas, New Solar Developments, Hellenic Petroleum Renewable Energy Sources, Egnatia Group, European Solar Farms Greece, Thessaloniki Energy Solar, Serres Power, Verde, Terna Energy, Siemens Gamesa, ABO Wind Hellas, Rensol Energy PV, Karatzis and Peloponnisiakos Anemos.

Applications submitted to RAE, the Regulatory Authority for Energy, between December, 2018 and June represent a total capacity of 8 GW. They number over 1,000, placing pressure on the processing demands at RAE, authority official Dionysis Papahristou noted.