RES installation permit deadline for producer certificate validity

The energy ministry’s RES licensing committee has proposed an additional deadline, for installation permit applications, as part of a second wave of interventions in the licensing simplification effort for new RES projects.

According to the proposal, if investors miss their installation permit application deadline, then producer certificates obtained for related projects would automatically expire.

Investors would be given a twelve-month period to submit their installation permit applications once connection offers have been accepted for solar energy projects, onshore wind farms and hybrid units, and 18 months for all other RES technologies and combined cooling, heart and power (CCHP) facilities, according to the committee’s proposal.