PPC using extra 58-MW unit on Crete for safety despite weak tourism data

Power utility PPC plans, next week, to begin operating 58-MW capacity generators leased and to be installed at a company power station even though electricity demand on the island is expected to be far lower than usual this summer.

The island will still need this generation boost to meet local energy requirements despite the pandemic’s anticipated negative impact on tourism, authorities have estimated.

Crete’s energy sufficiency situation will not be resolved until the island’s grid interconnection with Athens is completed.

The generators, to be installed at PPC’s power station at Atherinolakkos, southeastern Crete, are scheduled to begin operating on July 1.

PPC has received a production permit for the generators between July 1 and August 31. Depending on the conditions, this license could be stretched to also cover September.

Under normal circumstances, electricity demand on Crete typically reaches 700 MW during the summer as a result of major tourism development on the island. Power outages, both short and long-lasting, are a common summer occurrence on Crete.