North Macedonia involvement in key Alexandroupoli projects

North Macedonia plans to help cover its energy needs through an involvement in two Greek-based projects, the prospective FSRU in Alexandroupoli, northeastern Greece, and, in the same region, a gas-fueled power station to run on LNG stemming from the floating LNG terminal.

Much progress has been made on the neighboring country’s interest in these two projects since a meeting in Athens last September between Greek Prime Minister Kyriakos Mitsotakis and his North Macedonian counterpart Zoran Zaev. The partnership also represents a strategic decision for the Greek government.

It is considered certain that a state-owned North Macedonian company will soon enter the Alexandroupoli FSRU project’s equity pool with a 10 percent stake, energypress sources have informed.

This project’s five current partners – Copelouzos group, Gaslog, Greek gas utility DEPA, Greek gas grid operator DESFA and Bulgartransgaz – are expected to each offer small portions of their respective 20 percent stakes to make available a 10 percent stake for the state-owned North Macedonian company in the Alexandroupoli FSRU.

The project’s development is not expected to be impacted by any equity reshuffles.

Two international tenders staged by Gastrade, a company established by the Copelouzos group for the development and operation of the Alexandroupoli FSRU, have been successfully completed. One of the two tender concerns the FSRU’s construction. The other concerns the installation of pipelines linking this facility to the national gas grid.

The Alexandroupoli FSRU consortium is expected to make a final investment decision in late February, sources informed.

On the other front, ESM, North Macedonia’s state electricity company, is expected to acquire a 25 percent stake in a gas-fueled power station to be developed by Damco Energy, a Copelouzos group subsidiary, in Alexandroupoli’s industrial zone.

The initiative will secure 200 MW of the facility’s 800-MW capacity for North Macedonia. The country currently has an electricity deficit of approximately 2 GWh.

Bulgarian state-owned electricity company NEK EAD also appears interested in acquiring a stake in the Alexandroupoli power station. Bulgaria has projected an electricity deficit a few years from now as the country must phase out major lignite-fired power stations. European Commission exemptions extending the lifespans of these units are expiring.