One of three Crete link bidding teams wants time or will exit

ABB, the world’s biggest developer of power grid interconnection projects, has requested a further deadline extension greater than the one-month periods of additional time already granted twice for a tender concerning the Crete-Athens grid interconnection project’s engineering, procurement and construction of two converter stations and a GIS substation, energypress sources have informed. The tender’s current deadline is set to expire on October 31.

Both the Greek government and power grid operator IPTO appear determined not to accept any further deadline extension requests as this, they believe, would increase the risk of a project delay and, consequently, energy sufficiency issues on Crete.

Outdated, high-polluting power stations still operating on Crete soon need to be withdrawn.

ABB, which has joined forces with Greek maritime infrastructure construction and maintenance group Archirodon for the Cretan project’s tender, has cited the complexity of the project for the additional time the company appears to need. If a sizable extension is not granted, then ABB and project partner Archirodon will most likely withdraw from the tender, it is believed.

On the contrary, two other partnerships established for the tender, according to reliable sources, are preparing to submit their offers. Siemens is believed to have joined forces with Greek construction company TERNA and General Electric is working with Greece’s Mytilineos, according to sources.

The grid interconnection project’s development faces a tight schedule. IPTO chief executive Manos Manousakis told a recent conference the project will be launched early 2023, not at the end of 2022, as was previously believed.