Local and foreign upstream companies holding exploration and production licenses for hydrocarbon reserves on Greek territory, offshore and onshore, are awaiting Greek State reassurances for their ventures following a cabinet reshuffle that has resulted in a change of leadership at the energy ministry, bringing in Kostas Skrekas in place of Costis Hatzidakis.

Oil companies, delaying investment plans as a result of the pandemic and lower oil prices, are waiting for a vote of confidence from the Greek State, market sources insist.

The fall in oil prices, currently at levels of about 50 dollar a barrel, may have halted upstream investments internationally, but, nevertheless, this is a good time for resolving bureaucratic obstacles and preparing local communities for prospective exploration efforts that promise to contribute to job creation and economic recovery.

Four upstream investment plans are currently either at an advanced stage in terms of prospective drilling or at preliminary exploration stages.

Of all four plans, Energean’s license for Katakolo, western Greece, is at the most mature stage. Public consultation on an environmental impact study concerning this project’s drilling requirements was completed in December, 2019. The regional authority for western Greece has offered its approval. Even so, a year later, the energy ministry has yet to deliver its decision on the environmental study.

A license for the Gulf of Patras field, held by Hellenic Petroleum (ELPE) and Edison, is also at a mature stage. The partners requested, and were granted, an extension for the start of drilling at this field. EDEY, the Greek Hydrocarbon Management Company, granted the pair a further 15 months, until January 23, 2023, to facilitate their preparations.

Sources have attributed this additional time to a lack of appropriate regional port facilities, needed to facilitate the installation of equipment required for drilling. ELPE and Edison had previously been given another extension, until October, 2021.

On another front, a partnership comprising Repsol and Energean has until April to start a second stage of exploration activities at its Ioannina block in northwestern Greece. Local community approval is needed. The government needs to take action on the issue.

A fourth upstream project carrying geopolitical weight concerns licenses held by a consortium made up of Total, ExxonMobil and ELPE for offshore fields west and southwest of Crete. Though company representatives recently informed Crete’s regional authorities that seismic surveys are planned to begin towards spring, there have been no further updates or any signs of action.