Lignite-unit grid input rises, re-electrification a challenge

Virtually all of the country’s power generating facilities will be called into action today, even if below full capacity, to help meet grid needs and cover greater demand anticipated as areas disconnected during heavy snowfall over the past couple of days are gradually re-electrified, putting the system to the test.

Officials are confident the country’s power generating facilities will not have problems covering the day’s electricity demand.

According to power grid operator IPTO’s grid schedule, a significant number of lignite-fired power stations – Agios Dimitrios III and IV, Kardia III and IV, and Meliti – will operate today.

Also, given heightened electricity demand levels, expected to reach 8,190 MW, natural gas-fired power stations will be on stand-by for grid entry.

Power utility PPC’s Aliveri V, Lavrio IV and V, Komotini and Megalopoli V, plus a number of independent gas-fuelled units, Heron III, Elpedison’s units in Thessaloniki and Thisvi, and Protergia and Korinthos Power units, will be ready to contribute if needed.

RES output is expected to reach 27.185 GWh, while hydropower output is planned to total 36.132 GWh.

Overall production for the day is expected to reach 166.685 GWh, a lower level compared to yesterday.

Network distribution operator DEDDIE/HEDNO crews are working overtime to repair transmission lines that were damaged by hundreds of collapsing trees during heavy snowfall around the country over the past couple of days. This repair effort could require days to complete.

Some 400 DEDDIE/HEDNO technicians in Athens, bolstered by colleagues brought in from other parts of Greece, are currently working to re-electrify affected areas in the capital.