Distributor DEDA wants swifter delivery of operator projects

Gas distributor DEDA, covering all areas around Greece except for wider Athens, Thessaloniki and Thessaly, wants gas grid operator DESFA to complete key grid projects six months sooner so that the distributor may proceed with tenders for distribution network expansion projects.

DESFA needs to construct metering/regulating stations in Livadia, central Greece, as well as the Kastoria and Kozani regions in northern Greece.

DEDA called for a swifter delivery of these stations in public consultation staged for DESFA’s ten-year development plan covering 2021 to 2030.

DESFA plans to complete work on the Livadia metering/regulating station in March, 2022. However, DEDA has requested the station’s completion six months earlier, explaining it will not be able to distribute to consumers in the area until the station’s construction has been completed.

DEDA also called for the Kastoria and Kozani stations to be complete six months earlier, citing the same reasons.

In addition, DEDA requested the development of a natural gas compressor station close to the areas of Karpenisi, central Greece, and Amfissa, slightly southeast, to facilitate CNG supply to these regions.