IGB gas pipeline nearing launch, doubts dismissed

The prospective IGB gas pipeline linking Greece and Bulgaria is believed to be almost ready for its commercial launch, scheduled for October 1, despite recent doubts that were cast over the entire project.

Certain analysts recently questioned whether American LNG supply to Bulgaria, through the IGB pipeline, would go ahead, claiming the new Bulgarian government wants to renegotiate a supply agreement with Russia’s Gazprom.

ICGB AD, the consortium behind the IGB project has announced, in what is seen as a response to the scare, that an auction offering pipeline capacity to users will be held this Thursday through the online platform BALKAN GAS HUB EAD, from 9am to 12pm (Sofia time).

Greek construction company AVAX, developing the project, has set itself an end-of-August objective, which could be stretched to September 8, the latest, to complete pending work and obtain required permits from the Bulgarian authorities.

If all this goes according to plan, the IGB gas pipeline will be ready to operate on October 1.