Emergency steps taken for FSU at Revythoussa LNG terminal

The energy ministry appears to be pushing ahead with an emergency plan for swift installation of a floating storage unit (FSU) at the country’s only existing LNG terminal, on the islet Revythoussa, just off Athens, for increased LNG storage capacity ahead of next winter, sources have informed energypress.

Gas grid operator DESFA, the Revythoussa facility’s operator, has already researched the market for an appropriate vessel, which will need to be equipped with modern technology and recently built.

The FSU to be moored at Revythoussa will need to offer an LNG storage capacity of between 130,000 and 140,000 cubic meters to satisfy the Greek market’s needs, the sources noted.

Under normal conditions, procedures concerning this specific project would take over 12 months to complete and enable installation, but authorities are now moving fast as a result of the extreme impact Russia’s war on Ukraine has had on the energy market.

DESFA will present a cost-benefit analysis to the energy ministry by this Wednesday, according to sources.