DESFA, Windows International to battle for northern pipeline

Respective applications submitted by Windows International Hellas, an enterprise controlled by Russian entrepreneur Leonid Lebedev, and Greece’s gas grid operator DESFA for the development of a gas pipeline interconnection running from Greece’s north into North Macedonia have both been approved by RAE, the Regulatory Authority for Energy, viewing  the proposals as rival initiatives.

Windows International Hellas and DESFA will now need do to battle for the project’s contract.

RAE had approved the Windows International Hellas application in December, but the news was not disclosed until now, according to sources.

DESFA has been granted conditional approval for its ten-year development plan covering 2017 to 2026, which includes the gas pipeline interconnection, a project budgeted at 48.7 million euros. Full approval remains pending and depends on the results of a required market test.

Windows International Hellas intends to develop the pipeline as an independent natural gas system, which would not burden users, whereas DESFA wants to develop the project as part of the national natural gas system, which explains why RAE has called for a market test. The test will determine if sufficient demand exists to avoid burdening users.

Windows International Hellas wants to utilize the pipeline for coverage of North Macedonia’s domestic needs. The Lebedev-led firm plans to construct a gas-fueled power station, it has been rumored.

DESFA is aiming to connect with networks in other Balkan countries through the prospective gas pipeline.

It is planned to run from Nea Mesimvria in Thessaloniki to Gevgelija in North Macedonia.