DESFA market test for gas grid lift includes 3 pipeline doubles

Gas grid operator DESFA has begun preparing a market test for prospective gas transmission system expansion projects, based on a requirement set by RAE, the Regulatory Authority for Energy, as part of its approval of the projects.

The market test’s details are expected to be completed by the end of this month. A related event will then be staged to update gas transmission system users on the market test’s process as well as projects to be offered for capacity reservations.

RAE’s market test requirement for these projects has been incorporated into its approval of DESFA’s ten-year development plan covering 2022 to 2031, as the authority wants the operator to gauge the level of interest and need concerning the gas transmission system’s expansion.

According to energypress sources, three new gas pipelines, to serve as doubles at sections of the existing infrastructure, will be included in the market test.

One of the three pipelines is planned to complement infrastructure covering parts of the wider Athens area, a second pipeline is envisaged as a double for a pipeline running from Athens to Thessaloniki, and a third pipeline is planned to run as a double alongside a line from Thessaloniki to Komotini, northeastern Greece.

The EU’s decision to gradually diminish its reliance on Russian gas is changing the continent’s gas supply map. Subsequently, gas entry points from the continent’s south are now becoming more crucial, giving rise to the need for gas infrastructure boosts in Greece.