A plan by Damco Energy, a Copelouzos group subsidiary, to increase the capacity of its prospective natural gas-fired power station in Alexandroupoli, northeastern Greece, from 662 MW to 840 MW has been approved by RAE, the Regulatory Authority for Energy.

The energy company now needs to make an investment decision, expected within the summer, before work on the project commences, sources informed. Its licensing procedure has been completed.

According to the sources, ESM, North Macedonia’s state electricity company, set to acquire a 25 percent in the Alexandroupoli natural gas-fired power station, is now at the final of its preparations and is currently performing due diligence.

Damco Energy is one of a number of companies that have not only decided to develop natural gas-fired power stations but also to boost capacities of their respective projects to over 800 MW.

Mytilineos was the first to do so with its plan for an 826-MW combined cycle gas turbine (CCGT unit) in Agios Nikolaos, Viotia, northwest of Athens, a project already being developed.

Following suit, Elpedison upgraded a licensed natural gas-fired power station plan in Thessaloniki to 826 MW, while, just weeks ago, GEK Terna and Motor Oil also announced an upgrade for their natural gas-fired power station in Komotini, northeastern Greece, a joint venture, to 877 MW.

Power utility PPC has also announced a plan to convert its new lignite-fired power station, Ptolemaida V, to a natural gas unit, planned to ultimately offer a capacity of over 1,000 MW by 2025.

The prospective natural gas-fired power stations, totaling 4.3 GW, are planned to fill the capacity gap that will be left by PPC’s withdrawal of lignite-fired power stations, exiting as part of the country’s decarbonization effort.