Cyclades submarine interconnection enters final stage

The second phase of the Cyclades submarine cable interconnection has entered its final stage with the installation of cables from Evia to Andros and Andros to Tinos set to begin next week.

Italian company Prysmian, awarded the project by power grid operator IPTO, will begin work from Andros, energypress sources informed.

Existing power lines covering these two segments are being upgraded, for a capacity increase, at a cost of 21.2 million euros. Work on the two sections is expected to be completed by the end of this year, according to a contract signed between IPTO and Prysmian.

IPTO and the Italian firm had also collaborated for the Cyclades interconnection project’s first stage, linking coastal Lavrio, southeast of Athens, with Syros.

Just days ago, work was completed on the installation of a submarine cable linking the mainland with the Peloponnese at the Rio-Antirrio crossing. This project was undertaken by a consortium comprising Hellenic Cables and Fulgor.