Crete-Athens link tender set for further deadline extension

A tender concerning the Crete-Athens grid interconnection project’s engineering, procurement and construction of two converter stations and a GIS substation will be given a further deadline extension, possibly an entire month, as a result of requests made by major prospective bidders.

An initial August 30 deadline was reset for September 30 and may now be extended to October 30.

Project promoter Ariadne, a subsidiary of Greek power grid operator IPTO, has made clear to the tender’s participants the latest deadline extension will be the last as any further delays would place at risk the project’s completion on time. This would have repercussions as the project is vital for Crete’s energy sufficiency.

The latest extension is not linked to a legal challenge made by EuroAsia, a consortium of Cypriot interests heading a wider PCI-status project to link the Greek, Cypriot and Israeli grids, sources noted. Nor is it any way linked to a pending Greek government response to the European Commission on whether the Crete-Athens interconnection will be supported by Greece as part of the wider PCI project or as a national project, the sources added.

Some of the companies interested in the Crete-Athens link tender have confirmed requesting a new deadline extension.

This tender was preceded by an initial tender concerning the project’s cable segments. Appraisals of the technical aspects of offers will be completed by the end of this month, according to IPTO chief executive Manos Manousakis, while assessments of the financial offers will follow.