Amynteo silence adds to investor jitters over PPC sale

A decision by the main power utility PPC chief Manolis Panagiotakis to drop from a recent board meeting’s agenda the subject of a closure of the now-expired Amynteo lignite-fired power station is believed to have added to the ambiguity surrounding the utility’s relaunched sale package of lignite units.

Panagiotakis’ unexecuted announcement has been interpreted as an attempt to send out a positive message to investors as Anynteo’s eventual withdrawal from the grid would make other power stations units included in PPC’s sale package more competitive.

PPC is not planning an immediate withdrawal of Amynteo. The power plant’s closure is expected in late 2020 or early 2021, when a 32,000-hour extension offered by the government through a ministerial decision last November – as a further extension to Brussels’ 17,500 hours – should expire.

Investors eyeing PPC’s sale package, whose initial sale effort failed to produce a result, are still waiting for clarity on a number of issues.

Details remain pending on a profit and loss sharing mechanism expected to apply for the Meliti and Megalopoli units offered in the package. Investors are waiting to see these details in an updated SPA.

Also unclear are the developments of PPC’s effort for an improved lignite supply agreement with Lignitorihia Ahladas, the operator of the Ahlada mine feeding the Meliti power station. Improved price and quantity terms are being sought. Energy minister Giorgos Stathakis is mediating these talks.