Alexandroupoli FSRU 2Q investment decision, work to start in ’21

The shareholders of Gastrade, a company founded by the Copelouzos Group for the development and operation of the Alexandroupoli FSRU planned for Greece’s northeast, are gearing up for an investment decision, expected in the second quarter, ahead of the beginning of the project’s development, anticipated within the current year.

Gastrade’s shareholders will most likely make an investment decision in May, sources informed.

The consortium’s shareholders are currently awaiting final administrative details that will formalize the entry into Gastrade of Bulgaria’s Bulgartransgaz and DESFA, the Greek gas grid operator.

Last week, Thanassis Dagoumas, the head official at RAE, the Regulatory Authority for Energy, approved the transfer of a 20 percent Gastrade stake from the Copelouzos Group’s Asimina Eleni Copelouzou to the Bulgarian gas company.

Copelouzou now controls 40 percent of Gastrade, with three stakeholders, Gaslog, DEPA Commercial and Bulgartransgaz each holding 20 percent.

Within the next few weeks, the RAE chief is also expected to endorse a further 20 percent transfer from Copelouzou to DESFA, giving the consortium’s five partners equal shares of 20 percent each.

Gastrade has already announced a tender offering an EPC contract for the floating LNG terminal in Alexandroupoli. Participants face a February 18 deadline.

An investment decision promises to push forth engineering studies, including geotechnical, as well as the order of a floating vessel for the project during the year. The FSRU will be completed in 2023, Gastrade shareholders have announced.

The shareholders appear receptive to the idea of North Macedonian involvement in the Gastrade consortium. They are awaiting bilateral developments at a diplomatic level, sources informed.